335 N JUANITA AVE 1-49 90004

Certificate Information: 335 N JUANITA AVE 1-49 90004

Application / Permit
10010-10000-01041
Plan Check / Job No.
B10LA05633
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
4 LEVEL OF TYPE V OVER 1 LEVEL OF TYPE I APARTMENT BUILDING: 48 AFFORDABLE UNITS AND 1 TWO-BEDROOM MANAGER'S UNIT.
Permit Issued
Issued on 11/15/2010
Issuing Office
Metro
Current Status
CofO Issued on 3/28/2012
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/4/2010 APPLICANT
Assigned to Plan Check Engineer 6/10/2010 LARRY LEE
Corrections Issued 6/17/2010 LARRY LEE
Quality Review Completed 6/17/2010 COLIN KUMABE
Applicant returned to address corrections 6/22/2010 LARRY LEE
Applicant returned to address corrections 8/4/2010 LARRY LEE
Applicant returned to address corrections 8/11/2010 LARRY LEE
Applicant returned to address corrections 8/12/2010 LARRY LEE
Applicant returned to address corrections 8/13/2010 LARRY LEE
Applicant returned to address corrections 8/17/2010 LARRY LEE
Building Plans Picked Up 8/17/2010 APPLICANT
Disabled Access Plans Picked Up 8/17/2010 APPLICANT
Applicant returned to address corrections 8/18/2010 LARRY LEE
Applicant returned to address corrections 8/20/2010 LARRY LEE
Applicant returned to address corrections 8/24/2010 LARRY LEE
Applicant returned to address corrections 10/1/2010 LARRY LEE
Applicant returned to address corrections 10/19/2010 LARRY LEE
Plan Check Approved 10/26/2010 LARRY LEE
Issued 11/15/2010 LADBS
CofO in Progress 3/16/2012 SAKO AGHAZARIAN
Permit Finaled 3/28/2012 RICKEY JACKSON
CofO Issued 3/28/2012 RICKEY JACKSON
Permit Finaled 3/28/2012 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 6/22/2010 PAMELA TENEZA
Highway dedication Cleared 6/22/2010 NATALIE MOORE
Eng Process Fee Ord 176,300 Cleared 6/30/2010 AVALYN KAMACHI
Work Adjacent to Public Way Cleared 6/30/2010 HUEY CHU
Driveway location Cleared 7/9/2010 TAIMOUR TANAVOLI
Internal circulation Cleared 7/9/2010 TAIMOUR TANAVOLI
Building over 3-story or 36-ft Cleared 8/3/2010 CALOSHA APPROVED
Hydrant and Access approval Cleared 8/5/2010 JOHN DALLAS
Project located in CRA area Cleared 8/25/2010 JIM URQUHART
Housing density bonus Cleared 10/12/2010 ANGELES MOJICA
DAS Clearance Cleared 10/15/2010 WAI LAU
Density bonus per Sup. Crt dec Cleared 10/15/2010 CRAIG WEBER
Frnt yard landscape/Water mgmt Cleared 10/15/2010 CRAIG WEBER
Miscellaneous Cleared 10/15/2010 CRAIG WEBER
Opn space landscape/Water mgmt Cleared 10/15/2010 CRAIG WEBER
Specific Plan Cleared 10/15/2010 CRAIG WEBER
ZA Case Cleared 10/15/2010 CRAIG WEBER
ZA Case Cleared 10/15/2010 CRAIG WEBER
Sewer availability Cleared 10/19/2010 JAMES MORALEZ
Title 19 building approval Cleared 10/19/2010 GHASSEM NIKKHOO
Permit Cleared 10/26/2010 GREGG VANDERGRIFF
Roof/Waste drainage to street Cleared 10/26/2010 GREGG VANDERGRIFF
Stormwater Pollution Mitigatn Cleared 10/26/2010 AYMAN JABBOURI

Contact Information

Architect Killefer, Wade; Lic. No.: C10522 1625 OLYMPIC BLVD      SANTA MONICA, CA 90404
Contractor Portrait Homes Inc; Lic. No.: 615297-B 265 NORTH JOY STREET   SUITE 200    CORONA, CA 928791323
Engineer Labib, Youhanna T; Lic. No.: S4549 900 WILSHIRE BLVD STE 936      LOS ANGELES, CA 90017

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/19/2010 Partial Inspection JOHN CARPENTER
METHANE-Barrier 11/19/2010 Not Ready for Inspection JOHN CARPENTER
METHANE-Subgrade 11/19/2010 Not Ready for Inspection JOHN CARPENTER
Deputy Other (see comments) 12/15/2010 Conditional Approval SAKO AGHAZARIAN
Deputy Other (see comments) 12/17/2010 Conditional Approval SAKO AGHAZARIAN
Deputy Grading 1/12/2011 Conditional Approval SAKO AGHAZARIAN
Footing/Foundation/Slab 2/1/2011 Partial Inspection SAKO AGHAZARIAN
METHANE-Barrier 2/1/2011 Partial Inspection SAKO AGHAZARIAN
METHANE-Subgrade 2/1/2011 Partial Inspection SAKO AGHAZARIAN
Deputy Reinf. Concrete 2/2/2011 Conditional Approval SAKO AGHAZARIAN
Footing/Foundation/Slab 2/2/2011 Partial Approval SAKO AGHAZARIAN
METHANE-Rough 2/2/2011 Approved SAKO AGHAZARIAN
Verify Sprinkler Sign Off 2/2/2011 Not Ready for Inspection SAKO AGHAZARIAN
Deputy Reinf. Concrete 2/9/2011 Conditional Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 2/11/2011 Conditional Approval SAKO AGHAZARIAN
Special/Order Compliance 2/11/2011 Partial Inspection BENOIT BEAULIEU
Deputy Reinf. Concrete 2/14/2011 Conditional Approval SAKO AGHAZARIAN
Footing/Foundation/Slab 2/14/2011 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 2/15/2011 Conditional Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 2/23/2011 Conditional Approval SAKO AGHAZARIAN
Footing/Foundation/Slab 2/23/2011 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 2/24/2011 Conditional Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 2/25/2011 Conditional Approval SAKO AGHAZARIAN
Footing/Foundation/Slab 3/2/2011 Partial Inspection SAKO AGHAZARIAN
Deputy Reinf. Masonry 3/4/2011 Conditional Approval SAKO AGHAZARIAN
Deputy Shotcrete 3/4/2011 Conditional Approval SAKO AGHAZARIAN
Footing/Foundation/Slab 3/4/2011 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Masonry 3/9/2011 Conditional Approval SAKO AGHAZARIAN
Footing/Foundation/Slab 3/9/2011 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Masonry 3/10/2011 Conditional Approval SAKO AGHAZARIAN
Deputy Reinf. Masonry 3/11/2011 Conditional Approval SAKO AGHAZARIAN
Footing/Foundation/Slab 3/14/2011 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Masonry 3/15/2011 Conditional Approval SAKO AGHAZARIAN
Footing/Foundation/Slab 3/15/2011 Partial Inspection SAKO AGHAZARIAN
Verify Sprinkler Sign Off 3/15/2011 Partial Inspection SAKO AGHAZARIAN
Footing/Foundation/Slab 3/31/2011 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 4/8/2011 Conditional Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 4/11/2011 Conditional Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 4/12/2011 Conditional Approval SAKO AGHAZARIAN
Footing/Foundation/Slab 4/12/2011 Partial Approval SAKO AGHAZARIAN
Deputy Reinf. Concrete 4/14/2011 Conditional Approval SAKO AGHAZARIAN
Deputy Wood Construction 4/26/2011 Conditional Approval SAKO AGHAZARIAN
Deputy Wood Construction 4/27/2011 Conditional Approval JOHN CARPENTER
Verify Sprinkler Sign Off 4/27/2011 Not Ready for Inspection JOHN CARPENTER
Wood Frame 4/27/2011 Partial Inspection JOHN CARPENTER
Deputy Wood Construction 5/5/2011 Conditional Approval SAKO AGHAZARIAN
Deputy Steel/Welding 5/6/2011 Conditional Approval SAKO AGHAZARIAN
Verify Sprinkler Sign Off 5/6/2011 Partial Inspection SAKO AGHAZARIAN
Wood Frame 5/6/2011 Partial Approval SAKO AGHAZARIAN
Deputy Steel/Welding 5/10/2011 Conditional Approval SAKO AGHAZARIAN
Deputy Wood Construction 5/13/2011 Conditional Approval SAKO AGHAZARIAN
Verify Sprinkler Sign Off 5/13/2011 Partial Inspection SAKO AGHAZARIAN
Wood Frame 5/13/2011 Partial Inspection SAKO AGHAZARIAN
Deputy Steel/Welding 5/17/2011 Conditional Approval SAKO AGHAZARIAN
Deputy Steel/Welding 5/18/2011 Conditional Approval SAKO AGHAZARIAN
Deputy Steel/Welding 5/19/2011 Conditional Approval SAKO AGHAZARIAN
Deputy Steel/Welding 5/20/2011 Conditional Approval SAKO AGHAZARIAN
Verify Sprinkler Sign Off 5/27/2011 Partial Approval JONATHAN ALLEN
Wood Frame 5/27/2011 Partial Approval JONATHAN ALLEN
Deputy Steel/Welding 5/31/2011 Conditional Approval SAKO AGHAZARIAN
Deputy Steel/Welding 6/1/2011 Conditional Approval SAKO AGHAZARIAN
Verify Sprinkler Sign Off 6/1/2011 Not Ready for Inspection SAKO AGHAZARIAN
Wood Frame 6/1/2011 Conditional Approval SAKO AGHAZARIAN
Deputy Steel/Welding 6/2/2011 Conditional Approval SAKO AGHAZARIAN
Insulation 6/2/2011 Partial Inspection SAKO AGHAZARIAN
Deputy Steel/Welding 6/3/2011 Conditional Approval SAKO AGHAZARIAN
Verify Sprinkler Sign Off 6/7/2011 Approved SAKO AGHAZARIAN
Wood Frame 6/7/2011 Partial Inspection SAKO AGHAZARIAN
Insulation 6/16/2011 Partial Approval SAKO AGHAZARIAN
Deputy Steel/Welding 6/28/2011 Conditional Approval JOHN CARPENTER
Deputy Steel/Welding 6/29/2011 Conditional Approval MAURICE MARTINEZ
Deputy Steel/Welding 6/30/2011 Partial Approval WILLIAM GARCIA
Deputy Steel/Welding 7/1/2011 Partial Approval WILLIAM GARCIA
Wood Frame 7/6/2011 Approved SAKO AGHAZARIAN
Drywall Nailing 7/8/2011 Partial Approval SAKO AGHAZARIAN
Interior/Exterior Lathing 7/12/2011 Partial Approval SAKO AGHAZARIAN
Drywall Nailing 7/18/2011 Partial Approval SAKO AGHAZARIAN
Interior/Exterior Lathing 7/19/2011 Partial Inspection SAKO AGHAZARIAN
Interior/Exterior Lathing 7/21/2011 Approved SAKO AGHAZARIAN
Drywall Nailing 8/4/2011 Approved SAKO AGHAZARIAN
Deputy Reinf. Masonry 8/23/2011 Conditional Approval SAKO AGHAZARIAN
Final 10/17/2011 Partial Inspection SAKO AGHAZARIAN
Footing/Foundation/Slab 10/17/2011 Approved SAKO AGHAZARIAN
SGSOV-Seismic Gas S/O Valve 10/17/2011 SGSOV Approved SAKO AGHAZARIAN
Smoke Detectors 10/17/2011 Approved SAKO AGHAZARIAN
Final 11/18/2011 Partial Inspection SAKO AGHAZARIAN
Final 11/29/2011 Not Ready for Inspection JAMES POWERS
Insulation 11/30/2011 Approved SAKO AGHAZARIAN
Final 3/14/2012 OK to Issue CofO SAKO AGHAZARIAN