5354 N VANALDEN AVE 91356

Certificate Information: 5354 N VANALDEN AVE 91356

Application / Permit
09014-20000-00652
Plan Check / Job No.
B09VN01775
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EXPAND (E) BATHROOM AND ADD NEW CLOSET, 7'1"X23'7". ALL WORK PER ENGINEERED DETAILS.
Permit Issued
Issued on 3/6/2009
Issuing Office
Valley
Current Status
CofO Issued on 1/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/5/2009 APPLICANT
Assigned to Plan Check Engineer 3/5/2009 RODNEY SAMIIAN
Corrections Issued 3/5/2009 RODNEY SAMIIAN
Plan Check Approved 3/6/2009 RICHARD GARCIA
Issued 3/6/2009 LADBS
CofO in Progress 1/4/2024 SEAN WIRCH
CofO Issued 1/8/2024 JOHN JANSON
Permit Finaled 1/8/2024 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/6/2009 YERVAND CHAPANYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Hanbali, Amjad Moh'D; Lic. No.: C42213 514 W. COMMERCE AVE   SUITE F    PALMDALE, CA 93550

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/19/2009 Not Ready for Inspection ROBERT SHELLY
Footing/Foundation/Slab 3/19/2009 Not Ready for Inspection ROBERT SHELLY
Deputy Drilled-In Anchors 3/23/2009 No Access for Inspection ROBERT SHELLY
Excavation/Setback/Form/Re-Bar 3/31/2009 Not Ready for Inspection ROBERT SHELLY
Footing/Foundation/Slab 4/2/2009 Not Ready for Inspection ROBERT SHELLY
BUILDING-Rough-Frame 4/7/2009 Not Ready for Inspection ROBERT SHELLY
ELECTRICAL-Rough 4/24/2009 Not Ready for Inspection ROBERT SHELLY
HVAC-Rough 4/24/2009 Not Ready for Inspection ROBERT SHELLY
PLUMBING-Rough 4/24/2009 Not Ready for Inspection ROBERT SHELLY
ELECTRICAL-Rough 4/30/2009 Corrections Issued ROBERT SHELLY
HVAC-Rough 4/30/2009 Not Ready for Inspection ROBERT SHELLY
PLUMBING-Rough 4/30/2009 Approved ROBERT SHELLY
ELECTRICAL-Rough 5/1/2009 Approved ROBERT SHELLY
HVAC-Rough 5/1/2009 Approved ROBERT SHELLY
Wood Frame 5/7/2009 Not Ready for Inspection ROBERT SHELLY
BUILDING-Rough-Frame 5/8/2009 Approved ROBERT SHELLY
Insulation 5/14/2009 Approved ROBERT SHELLY
Drywall Nailing 5/26/2009 Not Ready for Inspection ROBERT SHELLY
Drywall Nailing 6/10/2009 Approved ROBERT SHELLY
Interior/Exterior Lathing 6/10/2009 Approved ROBERT SHELLY
Excavation/Setback/Form/Re-Bar 10/20/2009 Conditional Approval ROBERT SHELLY
Final 10/20/2009 Corrections Issued ROBERT SHELLY
Footing/Foundation/Slab 10/20/2009 Conditional Approval ROBERT SHELLY
SGSOV-Seismic Gas S/O Valve 10/20/2009 SGSOV Not Ready ROBERT SHELLY
Final 7/7/2010 No Access for Inspection ROBERT SHELLY
Smoke Detectors 7/7/2010 No Access for Inspection ROBERT SHELLY
Excavation/Setback/Form/Re-Bar 11/1/2011 Approved ROBERT SHELLY
Final 11/1/2011 Not Ready for Inspection ROBERT SHELLY
Footing/Foundation/Slab 11/1/2011 Approved ROBERT SHELLY
SGSOV-Seismic Gas S/O Valve 11/1/2011 SGSOV Approved ROBERT SHELLY
Special/Order Compliance 6/9/2023 Corrections Issued SEAN WIRCH
Final 12/1/2023 Not Ready for Inspection MORRIS JACKSON
Special/Order Compliance 12/14/2023 Corrections Issued SEAN WIRCH
Final 1/5/2024 OK to Issue CofO SEAN WIRCH