8734 N ETIWANDA AVE 91325
Certificate Information: 8734 N ETIWANDA AVE 91325
- Application / Permit
- 09014-10000-01396
- Plan Check / Job No.
- B09LA04107
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EXISTING STORAGE ROOM TO ADDITIONAL UNIT. APPROVED PER STATE ASSEMBLY BILL 1866, CHAPTER 1062, AMENDING GOVERNMENT CODE SECTIONS 65583.1, 65852.2, AND 65915.
- Permit Issued
- Issued on 11/12/2009
- Issuing Office
- Valley
- Current Status
- CofO Corrected on 11/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/5/2009 | APPLICANT |
| Assigned to Plan Check Engineer | 5/29/2009 | MERLAN LINARES |
| Corrections Issued | 6/9/2009 | MERLAN LINARES |
| Quality Review Completed | 6/16/2009 | JOHN VASQUEZ |
| Building Plans Picked Up | 6/23/2009 | APPLICANT |
| Plan Check Approved | 11/6/2009 | MERLAN LINARES |
| Issued | 11/12/2009 | LADBS |
| CofO in Progress | 10/7/2021 | JEFFREY PARD |
| CofO Issued-Status Void | 10/13/2021 | JOHN JANSON |
| Permit Finaled-Status Void | 10/13/2021 | JOHN JANSON |
| Re-Activate Permit | 10/14/2021 | JOHN JANSON |
| Permit Finaled | 11/10/2021 | JOHN JANSON |
| CofO Corrected | 11/10/2021 | JOHN JANSON |
| Permit Finaled | 11/10/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/10/2009 | WESLEY TANIJIRI |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2009 | NATALIE MOORE |
| Roof/Waste drainage to street | Cleared | 8/10/2009 | NATALIE MOORE |
| Sewer availability | Cleared | 8/10/2009 | NATALIE MOORE |
| Street width determination | Cleared | 8/10/2009 | WESLEY TANIJIRI |
| Highway dedication | Cleared | 8/26/2009 | THEIN HTAY |
| Miscellaneous | Cleared | 10/23/2009 | ALFREDO PEREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/21/2009 | Corrections Issued | ALFONSO AVILA |
| Excavation/Setback/Form/Re-Bar | 1/6/2010 | Partial Approval | ALFONSO AVILA |
| Footing/Foundation/Slab | 1/6/2010 | Partial Approval | ALFONSO AVILA |
| Excavation/Setback/Form/Re-Bar | 1/12/2010 | Approved | ALFONSO AVILA |
| Footing/Foundation/Slab | 1/12/2010 | Approved | ALFONSO AVILA |
| Gas Test | 1/13/2010 | Approved | ALFONSO AVILA |
| PLUMBING-Rough | 1/19/2010 | Corrections Issued | ALFONSO AVILA |
| Rough-Elec/Plmb/HVAC | 2/8/2010 | No Access for Inspection | ROBERT MINASSIANS |
| Rough-Elec/Plmb/HVAC | 2/9/2010 | Corrections Issued | ROBERT MINASSIANS |
| ELECTRICAL-Rough | 2/17/2010 | Not Ready for Inspection | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2010 | Partial Approval | DONALD SUNSERI |
| PLUMBING-Rough | 2/17/2010 | Partial Inspection | DONALD SUNSERI |
| Underground Mechanical | 2/18/2010 | Approved | DONALD SUNSERI |
| ELECTRICAL-Rough | 2/22/2010 | Approved | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2010 | Approved | DONALD SUNSERI |
| HVAC-Rough | 2/22/2010 | Approved | DONALD SUNSERI |
| Insulation | 2/22/2010 | Approved | DONALD SUNSERI |
| PLUMBING-Rough | 2/22/2010 | Approved | DONALD SUNSERI |
| Wood Frame | 2/22/2010 | Conditional Approval | DONALD SUNSERI |
| Drywall Nailing | 3/2/2010 | Approved | DONALD SUNSERI |
| Interior/Exterior Lathing | 3/2/2010 | Not Ready for Inspection | DONALD SUNSERI |
| Interior/Exterior Lathing | 3/10/2010 | Corrections Issued | DONALD SUNSERI |
| Interior/Exterior Lathing | 3/15/2010 | Approved | DONALD SUNSERI |
| Final | 5/19/2010 | Corrections Issued | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 5/19/2010 | SGSOV Not Ready | WILLIAM KUEHN |
| Smoke Detectors | 5/19/2010 | Approved | WILLIAM KUEHN |
| Final | 5/27/2010 | Corrections Issued | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 5/27/2010 | SGSOV Not Ready | WILLIAM KUEHN |
| ELECTRICAL-Final | 6/3/2010 | Approved | WILLIAM KUEHN |
| Final | 6/3/2010 | Conditional Approval | WILLIAM KUEHN |
| HVAC-Final | 6/3/2010 | Approved | WILLIAM KUEHN |
| PLUMBING-Final | 6/3/2010 | Approved | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 6/3/2010 | SGSOV Approved | WILLIAM KUEHN |
| Final | 9/12/2012 | Corrections Issued | WILLIAM KUEHN |
| Final | 6/18/2021 | Corrections Issued | JEFFREY PARD |
| Final | 8/18/2021 | Partial Approval | JEFFREY PARD |