5905 W WILSHIRE BLVD 90036

Certificate Information: 5905 W WILSHIRE BLVD 90036

Application / Permit
08044-10000-07609
Plan Check / Job No.
M08LA03007
Group
Mechanical
Type
HVAC
Sub-Type
Commercial
Primary Use
()
Work Description
Providing 4 new air handlers for new museum gallery building tapped off of existing central plant. Included is a modification for reducing the required min distance of garage exhaust outlet.
Permit Issued
Issued on 9/30/2008
Issuing Office
Metro
Current Status
Permit Finaled on 5/19/2010

Permit Application Status History

Submitted 7/29/2008 APPLICANT
Assigned to Plan Check Engineer 7/31/2008 MANOUCHEHR SHAHRESTANI
Corrections Issued 8/9/2008 MANOUCHEHR SHAHRESTANI
Plan Check Approved 9/30/2008 MANOUCHEHR SHAHRESTANI
Issued 9/30/2008 LADBS
Permit Finaled 5/18/2010 RICHARD HARWOOD

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Acco Engineered Systems Inc; Lic. No.: 120696-C20 6265 SAN FERNANDO RD      GLENDALE, CA 91201
Contractor Matt Construction Corporation; Lic. No.: 631020-B 9814 NORWALK BLVD #100      SANTA FE SPRINGS, CA 90670
Engineer Mc, Conahey Erin Kathleen; Lic. No.: M31244 5745 LEMONA AVE      VAN NUYS, CA 91411

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Rough-A/C and Heating 12/3/2008 Not Ready for Inspection RICK HARWOOD
Fire Damper Framing 3/18/2009 Partial Inspection RICK HARWOOD
Rough-A/C and Heating 3/18/2009 Partial Inspection RICK HARWOOD
Rough-A/C and Heating 3/23/2009 Partial Approval RICK HARWOOD
Rough-A/C and Heating 4/1/2009 Partial Approval RICK HARWOOD
Rough-Ventilation 4/1/2009 Partial Inspection RICK HARWOOD
Rough-Ventilation 4/3/2009 Partial Inspection RICK HARWOOD
Pre-Wrap Duct Insp 4/10/2009 Partial Approval RICK HARWOOD
Rough-A/C and Heating 4/10/2009 Partial Approval RICK HARWOOD
Rough-Ventilation 4/10/2009 Partial Approval RICK HARWOOD
Pre-Wrap Duct Insp 4/14/2009 Partial Approval RICK HARWOOD
Rough-A/C and Heating 4/14/2009 Partial Approval RICK HARWOOD
Rough-A/C and Heating 4/20/2009 Partial Approval RICK HARWOOD
Rough-A/C and Heating 4/28/2009 Partial Approval STEVE ARCHER
Rough-A/C and Heating 5/4/2009 Partial Approval RICK HARWOOD
Rough-A/C and Heating 5/8/2009 Partial Approval RICK HARWOOD
Rough-A/C and Heating 8/3/2009 Partial Approval RICK HARWOOD
Rough-AC/Htng/Vent 8/21/2009 No Access for Inspection RICK HARWOOD
Rough-AC/Htng/Vent 8/25/2009 Partial Approval RICK HARWOOD
Fire Damper Framing 9/17/2009 Partial Approval RICK HARWOOD
Fire Damper Framing 9/24/2009 Partial Approval RICK HARWOOD
Rough-AC/Htng/Vent 9/24/2009 Partial Inspection RICK HARWOOD
Fire Damper Framing 10/20/2009 Partial Approval RICK HARWOOD
Rough-AC/Htng/Vent 10/20/2009 Partial Approval RICK HARWOOD
Rough-Ventilation 11/6/2009 Partial Inspection RICK HARWOOD
Rough-A/C and Heating 11/18/2009 Partial Inspection RICK HARWOOD
Rough-A/C and Heating 11/19/2009 Partial Approval RICK HARWOOD
Rough-A/C and Heating 11/24/2009 Partial Approval KEVIN KIDD
Rough-A/C and Heating 12/4/2009 Partial Approval RICK HARWOOD
Rough-A/C and Heating 12/14/2009 Partial Approval RICK HARWOOD
Rough-A/C and Heating 1/5/2010 Partial Approval RICK HARWOOD
Rough-AC/Htng/Vent 2/23/2010 Partial Approval RICK HARWOOD
Final 3/30/2010 Partial Approval STEVEN PALCHANIS
Final 4/6/2010 Corrections Issued RICK HARWOOD
Final 4/6/2010 Partial Approval RICK HARWOOD
Final 4/7/2010 Partial Inspection RICK HARWOOD
Test-Life Sfty/Vent/Smoke/Air 4/7/2010 Partial Approval RICK HARWOOD
Final 5/18/2010 Permit Finaled RICK HARWOOD