2029 S CENTURY PARK EAST 34TH FLR 90067
Certificate Information: 2029 S CENTURY PARK EAST 34TH FLR 90067
- Application / Permit
- 08016-10000-11729
- Plan Check / Job No.
- B08LA06381
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- T. I. ADD NON-BEARING WALLS AND SUSPENDED CEILING TO CREATE OFFICE SPACES, FOR THE ENTIRE FLOOR. REINFORCE FLOOR FRAMING AT FLOOR CORES.
- Permit Issued
- Issued on 10/21/2008
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 6/18/2009
Permit Application Status History
| Submitted | 7/11/2008 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2008 | ARMANDO MEDINA |
| Corrections Issued | 7/22/2008 | ARMANDO MEDINA |
| Plan Check Approved | 7/22/2008 | ARMANDO MEDINA |
| Issued | 10/21/2008 | LADBS |
| Permit Finaled | 6/17/2009 | FRANK BOYLE |
Permit Application Clearance Information
| Title 19 building approval | Cleared | 7/22/2008 | GHASSEM NIKKHOO |
Contact Information
| Architect | Cohen, Andrew Phillip; Lic. No.: C12855 | 2500 BROADWAY STE 300 SANTA MONICA, CA 90404 |
| Contractor | Clune Construction Company L P; Lic. No.: 732107-B | 350 SOUTH GRAND AVE #1670 LOS ANGELES, CA 90071 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 2/3/2009 | Partial Approval | FRANK BOYLE |
| Light Gage Steel Frame | 2/3/2009 | Partial Approval | FRANK BOYLE |
| Wall Anchors | 2/3/2009 | Partial Approval | FRANK BOYLE |
| Drywall Nailing | 2/13/2009 | Partial Approval | TONY HARTONO |
| Insulation | 2/18/2009 | Partial Approval | FRANK BOYLE |
| Wood Frame | 2/18/2009 | Partial Approval | FRANK BOYLE |
| Excavation/Setback/Form/Re-Bar | 3/25/2009 | Partial Approval | FRANK BOYLE |
| Deputy Steel/Welding | 4/6/2009 | Approved | FRANK BOYLE |
| Drywall Nailing | 5/26/2009 | Partial Approval | FRANK BOYLE |
| Insulation | 5/26/2009 | Partial Approval | FRANK BOYLE |
| Light Gage Steel Frame | 5/26/2009 | Partial Approval | FRANK BOYLE |
| T-Bar Ceiling | 5/26/2009 | Partial Approval | FRANK BOYLE |
| Drywall Nailing | 6/17/2009 | Approved | FRANK BOYLE |
| Final | 6/17/2009 | Permit Finaled | FRANK BOYLE |
| SGSOV-Seismic Gas S/O Valve | 6/17/2009 | SGSOV Approved | FRANK BOYLE |
| Wood Frame | 6/17/2009 | Approved | FRANK BOYLE |