19259 W CASA PL 91356
Certificate Information: 19259 W CASA PL 91356
- Application / Permit
- 08014-20001-02298
- Plan Check / Job No.
- B09VN08195
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND 3-STORY ADDITION TO (E) 2 STORY SFD W/ ATTACHED GARAGE. COMPLY WITH DEPARTMENT ORDER effective date 10/06/2008. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE. ***REVISE ARCHITECTURAL/ STRUCTURAL PLANS ALSO ADD ADDITIONAL AREA & FIVE STEEL FRAMES***
- Permit Issued
- Issued on 9/28/2009
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 7/17/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/26/2009 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2009 | ARA SARGSYAN |
| Corrections Issued | 9/17/2009 | ARA SARGSYAN |
| Quality Review Completed | 9/18/2009 | DOUGLAS NAKATANI |
| Building Plans Picked Up | 9/18/2009 | APPLICANT |
| Plan Check Approved | 9/25/2009 | ARA SARGSYAN |
| Issued | 9/28/2009 | LADBS |
| Permit Expired | 9/29/2011 | BOBBY SHELLY |
| Permit Finaled | 7/17/2025 | JOHN KIDWELL |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2009 | LIONEL GIBSON |
| Sewer availability | Cleared | 9/22/2009 | LIONEL GIBSON |
| VHFHSZ | Cleared | 9/22/2009 | JOSEPH JACKSON |
| Public Works-Highway Ded. | Cleared | 9/22/2009 | LIONEL GIBSON |
| Public Works-Open Permits | Cleared | 9/22/2009 | LIONEL GIBSON |
| Public Works-Sewers | Cleared | 9/22/2009 | LIONEL GIBSON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
| Engineer | Beck, Victor P; Lic. No.: C12521 | 20821 HORACE ST CHATSWORTH, CA 91311 |
| Engineer | Rybak, Richard; Lic. No.: GE2131 | 17168 SAN FERNANDO MISSION BLVD GRANADA HILLS, CA 91344 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/30/2009 | Not Ready for Inspection | ROBERT SHELLY |
| Underground Mechanical | 10/20/2009 | Not Ready for Inspection | ROBERT SHELLY |
| Underground Mechanical | 10/21/2009 | Approved | ROBERT SHELLY |
| Footing/Foundation/Slab | 10/27/2009 | Corrections Issued | ROBERT SHELLY |
| Footing/Foundation/Slab | 10/29/2009 | Partial Approval | ROBERT SHELLY |
| Deputy Reinf. Concrete | 10/30/2009 | Conditional Approval | ROBERT SHELLY |
| Footing/Foundation/Slab | 11/20/2009 | Partial Approval | ROBERT SHELLY |
| Underground Mechanical | 11/20/2009 | Approved | ROBERT SHELLY |
| Deputy Reinf. Concrete | 11/24/2009 | Conditional Approval | ROBERT SHELLY |
| Footing/Foundation/Slab | 12/4/2009 | Partial Approval | ROBERT SHELLY |
| Footing/Foundation/Slab | 12/8/2009 | Approved | ROBERT SHELLY |
| Deputy Steel/Welding | 4/20/2010 | Approved | ROBERT SHELLY |
| Pre-Inspection | 4/20/2010 | Approved | ROBERT SHELLY |
| Deputy Steel/Welding | 4/21/2010 | Conditional Approval | ROBERT SHELLY |
| Structural Steel Frame | 4/27/2010 | Approved | ROBERT SHELLY |
| BUILDING-Rough-Frame | 5/6/2010 | Partial Approval | ROBERT SHELLY |
| BUILDING-Rough-Frame | 5/11/2010 | Partial Approval | ROBERT SHELLY |
| BUILDING-Rough-Frame | 6/15/2010 | Partial Approval | ROBERT SHELLY |
| BUILDING-Rough-Frame | 7/26/2010 | Not Ready for Inspection | ROBERT SHELLY |
| BUILDING-Rough-Frame | 9/14/2010 | Not Ready for Inspection | ROBERT SHELLY |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2010 | Not Ready for Inspection | ROBERT SHELLY |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2010 | Partial Approval | ROBERT SHELLY |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2010 | Partial Approval | ROBERT SHELLY |
| PLUMBING-Rough | 12/9/2010 | Approved | ROBERT SHELLY |
| HVAC-Rough | 1/6/2011 | Approved | ROBERT SHELLY |
| Wood Frame | 1/6/2011 | Partial Approval | ROBERT SHELLY |
| BUILDING-Rough-Frame | 1/7/2011 | Partial Inspection | ROBERT SHELLY |
| ELECTRICAL-Rough | 1/12/2011 | Approved | ROBERT SHELLY |
| Wood Frame | 1/13/2011 | Not Ready for Inspection | ROBERT SHELLY |
| BUILDING-Rough-Frame | 1/21/2011 | Partial Approval | ROBERT SHELLY |
| Insulation | 2/23/2011 | Approved | ROBERT SHELLY |
| Interior/Exterior Lathing | 2/23/2011 | Partial Approval | ROBERT SHELLY |
| BUILDING-Rough-Frame | 4/12/2011 | Partial Inspection | ROBERT SHELLY |
| Drywall Nailing | 4/12/2011 | Partial Approval | ROBERT SHELLY |
| BUILDING-Rough-Frame | 4/15/2011 | Approved | ROBERT SHELLY |
| Drywall Nailing | 4/15/2011 | Partial Approval | ROBERT SHELLY |
| Interior/Exterior Lathing | 5/17/2011 | Approved | ROBERT SHELLY |
| Drywall Nailing | 9/28/2011 | Not Ready for Inspection | ROBERT SHELLY |
| Final | 9/28/2011 | Permit Expired | ROBERT SHELLY |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2011 | Approved | ROBERT SHELLY |
| Smoke Detectors | 9/28/2011 | Not Ready for Inspection | ROBERT SHELLY |