5737 S 5TH AVE 90043
Certificate Information: 5737 S 5TH AVE 90043
- Application / Permit
- 08010-70000-01174
- Plan Check / Job No.
- B08SL00836
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- New detached two-car garage. Construction per type V sheet, P/BC 2008-004. Related electrical.
- Permit Issued
- Issued on 5/19/2008
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 1/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2008 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2008 | PATRICK KONG |
| Corrections Issued | 5/13/2008 | PATRICK KONG |
| Applicant returned to address corrections | 5/15/2008 | PATRICK KONG |
| Issued | 5/19/2008 | LADBS |
| CofO in Progress | 12/19/2024 | LUIS CASTRO |
| Permit Finaled | 1/12/2025 | DEROLD HAUFF |
| CofO Issued | 1/12/2025 | DEROLD HAUFF |
| Permit Finaled | 1/12/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/6/2008 | Corrections Issued | COREY HUPP |
| Footing/Foundation/Slab | 8/14/2008 | Approved | ROBERT MCDOWELL |
| Rough-Frame | 9/23/2008 | Not Ready for Inspection | ADRIAN GAUTHIER |
| Rough-Frame | 9/25/2008 | Not Ready for Inspection | ADRIAN GAUTHIER |
| Rough-Frame | 10/2/2008 | Corrections Issued | ADRIAN GAUTHIER |
| Pre-Inspection | 10/7/2008 | Corrections Issued | ADRIAN GAUTHIER |
| Rough-Frame | 10/14/2008 | No Access for Inspection | FELIPE PENICHE |
| Pre-Inspection | 10/15/2008 | Approved | ADRIAN GAUTHIER |
| Rough-Frame | 11/25/2008 | Not Ready for Inspection | LUIS BARRALES |
| Rough-Frame | 12/18/2008 | Corrections Issued | LUIS BARRALES |
| Wood Frame | 1/12/2009 | Not Ready for Inspection | LUIS BARRALES |
| Wood Frame | 5/20/2009 | Not Ready for Inspection | LUIS BARRALES |
| BUILDING-Rough-Frame | 7/9/2009 | Approved | LUIS BARRALES |
| ELECTRICAL-Rough | 7/9/2009 | Approved | LUIS BARRALES |
| Drywall Nailing | 12/31/2009 | Approved | LUIS BARRALES |
| Final | 12/31/2009 | Not Ready for Inspection | LUIS BARRALES |
| SGSOV-Seismic Gas S/O Valve | 12/31/2009 | SGSOV Approved | LUIS BARRALES |
| Wood Frame | 12/31/2009 | Approved | LUIS BARRALES |
| Final | 5/17/2012 | No Access for Inspection | HAL FULTZ |
| Special/Order Compliance | 8/21/2024 | Corrections Issued | ANTHONY EGSON |
| Final | 11/4/2024 | Not Ready for Inspection | BARRY HACHE |
| Final | 11/20/2024 | Not Ready for Inspection | BARRY HACHE |
| Final | 12/5/2024 | Conditional Approval | BARRY HACHE |
| Final | 12/16/2024 | Corrections Issued | BARRY HACHE |
| Final | 12/18/2024 | OK to Issue CofO | LUIS CASTRO |