Pre-Inspection
|
5/3/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Grading
|
6/13/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
6/13/2013
|
Partial Approval
|
JAMES POWERS
|
Excavation/Setback/Form/Re-Bar
|
6/13/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
6/14/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
6/17/2013
|
Approved
|
MICHAEL KUHN
|
Excavation/Setback/Form/Re-Bar
|
6/17/2013
|
Not Ready for Inspection
|
MICHAEL KUHN
|
Deputy Reinf. Concrete
|
6/18/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Shotcrete
|
6/18/2013
|
Partial Approval
|
JAMES POWERS
|
Excavation/Setback/Form/Re-Bar
|
6/18/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
6/19/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
6/20/2013
|
Partial Approval
|
JAMES POWERS
|
Excavation/Setback/Form/Re-Bar
|
6/20/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
6/21/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
6/24/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
6/25/2013
|
Partial Approval
|
JAMES POWERS
|
Footing/Foundation/Slab
|
6/25/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
6/26/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
6/27/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Shotcrete
|
6/27/2013
|
Partial Approval
|
JAMES POWERS
|
Excavation/Setback/Form/Re-Bar
|
6/27/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
6/28/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Shotcrete
|
6/28/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
7/3/2013
|
Partial Approval
|
JAMES POWERS
|
Footing/Foundation/Slab
|
7/3/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
7/5/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
7/9/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Shotcrete
|
7/10/2013
|
Partial Approval
|
JAMES POWERS
|
Excavation/Setback/Form/Re-Bar
|
7/10/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
7/11/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Shotcrete
|
7/11/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
7/12/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Shotcrete
|
7/12/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Shotcrete
|
7/15/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Shotcrete
|
7/16/2013
|
Partial Approval
|
JAMES POWERS
|
Reinforced Concrete Frame
|
7/16/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
7/17/2013
|
Conditional Approval
|
WINFIELD HINKSON
|
Deputy Shotcrete
|
7/17/2013
|
Conditional Approval
|
WINFIELD HINKSON
|
Deputy Shotcrete
|
7/18/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Shotcrete
|
7/19/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Shotcrete
|
7/23/2013
|
Partial Approval
|
JAMES POWERS
|
Excavation/Setback/Form/Re-Bar
|
7/23/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Shotcrete
|
7/24/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Shotcrete
|
7/25/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Shotcrete
|
7/26/2013
|
Partial Approval
|
JAMES POWERS
|
Footing/Foundation/Slab
|
7/26/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Shotcrete
|
7/29/2013
|
Partial Approval
|
JAMES POWERS
|
Excavation/Setback/Form/Re-Bar
|
7/29/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Shotcrete
|
7/30/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Shotcrete
|
8/8/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Steel/Welding
|
8/9/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
8/12/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
8/13/2013
|
Partial Approval
|
JAMES POWERS
|
Footing/Foundation/Slab
|
8/14/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
8/15/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Shotcrete
|
8/19/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Shotcrete
|
8/20/2013
|
Partial Approval
|
JAMES POWERS
|
Footing/Foundation/Slab
|
8/20/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Shotcrete
|
8/21/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Shotcrete
|
8/22/2013
|
Partial Approval
|
JAMES POWERS
|
Reinforced Concrete Frame
|
8/22/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Shotcrete
|
8/23/2013
|
Partial Approval
|
JAMES POWERS
|
Excavation/Setback/Form/Re-Bar
|
8/23/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
8/26/2013
|
Approved
|
DERRICK SPENCER
|
Deputy Shotcrete
|
8/26/2013
|
Approved
|
DERRICK SPENCER
|
Deputy Shotcrete
|
9/16/2013
|
Partial Approval
|
JAMES POWERS
|
Reinforced Concrete Frame
|
9/16/2013
|
Partial Approval
|
JAMES POWERS
|
Footing/Foundation/Slab
|
9/23/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
9/24/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
10/10/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
10/11/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
10/15/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
10/22/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
10/23/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
10/24/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
10/25/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
10/28/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
10/29/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
10/30/2013
|
Partial Approval
|
JAMES POWERS
|
Reinforced Concrete Frame
|
10/30/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
10/31/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
11/1/2013
|
Partial Approval
|
JAMES POWERS
|
Reinforced Concrete Frame
|
11/1/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
11/4/2013
|
Partial Approval
|
LESLIE TRUJILLO
|
Deputy Reinf. Concrete
|
11/5/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
11/6/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
11/7/2013
|
Partial Approval
|
JAMES POWERS
|
Reinforced Concrete Frame
|
11/7/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
11/8/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
11/18/2013
|
Partial Approval
|
JAMES POWERS
|
Footing/Foundation/Slab
|
11/18/2013
|
Not Ready for Inspection
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
11/19/2013
|
Approved
|
MICHAEL KUHN
|
Excavation/Setback/Form/Re-Bar
|
11/19/2013
|
Partial Approval
|
MICHAEL KUHN
|
Footing/Foundation/Slab
|
11/20/2013
|
Partial Approval
|
JAMES POWERS
|
Floor/Roof Diaphrgm/Shear Wall
|
11/25/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Steel/Welding
|
12/4/2013
|
Partial Approval
|
JAMES POWERS
|
Floor/Roof Diaphrgm/Shear Wall
|
12/6/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Steel/Welding
|
12/9/2013
|
Partial Approval
|
JAMES POWERS
|
Deputy Wood Construction
|
12/18/2013
|
Partial Approval
|
JAMES POWERS
|
Floor/Roof Diaphrgm/Shear Wall
|
12/18/2013
|
Partial Approval
|
JAMES POWERS
|
Floor/Roof Diaphrgm/Shear Wall
|
1/3/2014
|
Partial Approval
|
JAMES POWERS
|
Deputy Wood Construction
|
1/7/2014
|
Partial Approval
|
JAMES POWERS
|
Floor/Roof Diaphrgm/Shear Wall
|
1/7/2014
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
1/14/2014
|
Partial Approval
|
JAMES POWERS
|
Floor/Roof Diaphrgm/Shear Wall
|
1/16/2014
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
1/17/2014
|
Partial Approval
|
JAMES POWERS
|
Deputy Reinf. Concrete
|
1/22/2014
|
Partial Approval
|
JAMES POWERS
|
Floor/Roof Diaphrgm/Shear Wall
|
1/22/2014
|
Partial Approval
|
JAMES POWERS
|
Masonry Wall/Backfill
|
1/22/2014
|
Partial Approval
|
JAMES POWERS
|
Floor/Roof Diaphrgm/Shear Wall
|
1/30/2014
|
Approved
|
MICHAEL ALVAREZ
|
Deputy Reinf. Concrete
|
2/6/2014
|
Partial Approval
|
JAMES POWERS
|
Floor/Roof Diaphrgm/Shear Wall
|
2/6/2014
|
Partial Approval
|
JAMES POWERS
|
Masonry Wall/Backfill
|
2/6/2014
|
Partial Approval
|
JAMES POWERS
|
Floor/Roof Diaphrgm/Shear Wall
|
2/12/2014
|
Partial Approval
|
JAMES POWERS
|
Deputy Wood Construction
|
2/20/2014
|
Partial Approval
|
JAMES POWERS
|
Floor/Roof Diaphrgm/Shear Wall
|
2/20/2014
|
Partial Approval
|
JAMES POWERS
|
Masonry Wall/Backfill
|
2/25/2014
|
Partial Approval
|
JAMES POWERS
|
Floor/Roof Diaphrgm/Shear Wall
|
2/27/2014
|
Partial Approval
|
JAMES POWERS
|
Floor/Roof Diaphrgm/Shear Wall
|
3/13/2014
|
Partial Approval
|
JAMES POWERS
|
Floor/Roof Diaphrgm/Shear Wall
|
3/18/2014
|
Partial Approval
|
JAMES POWERS
|
Wood Frame
|
3/24/2014
|
Partial Approval
|
JAMES POWERS
|
Insulation
|
3/28/2014
|
Partial Approval
|
JAMES POWERS
|
Drywall Nailing
|
4/4/2014
|
Not Ready for Inspection
|
BYRON FUENTES
|
Insulation
|
4/4/2014
|
Partial Approval
|
BYRON FUENTES
|
Drywall Nailing
|
4/7/2014
|
Partial Approval
|
BYRON FUENTES
|
Floor/Roof Diaphrgm/Shear Wall
|
4/9/2014
|
Partial Approval
|
JAMES POWERS
|
Drywall Nailing
|
4/17/2014
|
Partial Approval
|
JAMES POWERS
|
Floor/Roof Diaphrgm/Shear Wall
|
4/17/2014
|
Partial Approval
|
JAMES POWERS
|
Insulation
|
4/22/2014
|
Partial Approval
|
JAMES POWERS
|
Insulation
|
4/24/2014
|
Partial Approval
|
JAMES POWERS
|
Insulation
|
4/30/2014
|
Partial Approval
|
BYRON FUENTES
|
Insulation
|
5/5/2014
|
Partial Approval
|
JAMES POWERS
|
Drywall Nailing
|
5/8/2014
|
Not Ready for Inspection
|
MICHAEL KUHN
|
Insulation
|
5/8/2014
|
Partial Inspection
|
MICHAEL KUHN
|
Insulation
|
5/9/2014
|
Partial Approval
|
JAMES POWERS
|
Deputy Wood Construction
|
5/13/2014
|
Approved
|
MICHAEL KUHN
|
Floor/Roof Diaphrgm/Shear Wall
|
5/13/2014
|
Partial Approval
|
MICHAEL KUHN
|
Deputy Wood Construction
|
5/14/2014
|
Approved
|
MICHAEL KUHN
|
Insulation
|
5/14/2014
|
Partial Approval
|
MICHAEL KUHN
|
Insulation
|
5/15/2014
|
Partial Approval
|
MICHAEL KUHN
|
Insulation
|
5/19/2014
|
Not Ready for Inspection
|
BYRON FUENTES
|
Interior/Exterior Lathing
|
5/19/2014
|
Not Ready for Inspection
|
BYRON FUENTES
|
Insulation
|
5/20/2014
|
Partial Approval
|
JAMES POWERS
|
Interior/Exterior Lathing
|
5/20/2014
|
Partial Approval
|
JAMES POWERS
|
Wood Frame
|
5/20/2014
|
Partial Approval
|
JAMES POWERS
|
Insulation
|
5/21/2014
|
Partial Approval
|
JAMES POWERS
|
Insulation
|
5/22/2014
|
Partial Approval
|
BYRON FUENTES
|
Insulation
|
5/27/2014
|
Partial Approval
|
BYRON FUENTES
|
Interior/Exterior Lathing
|
5/27/2014
|
Partial Approval
|
BYRON FUENTES
|
Deputy Wood Construction
|
5/28/2014
|
Partial Approval
|
JAMES POWERS
|
Floor/Roof Diaphrgm/Shear Wall
|
5/29/2014
|
Partial Approval
|
JAMES POWERS
|
Insulation
|
5/29/2014
|
Partial Approval
|
JAMES POWERS
|
Interior/Exterior Lathing
|
5/29/2014
|
Partial Approval
|
JAMES POWERS
|
Insulation
|
6/2/2014
|
Partial Approval
|
JAMES POWERS
|
Wood Frame
|
6/2/2014
|
Not Ready for Inspection
|
JAMES POWERS
|
Insulation
|
6/4/2014
|
Partial Approval
|
JAMES POWERS
|
Wood Frame
|
6/4/2014
|
Partial Approval
|
JAMES POWERS
|
Drywall Nailing
|
6/6/2014
|
Not Ready for Inspection
|
JAMES POWERS
|
Insulation
|
6/6/2014
|
Partial Approval
|
JAMES POWERS
|
Insulation
|
6/10/2014
|
Not Ready for Inspection
|
JAMES POWERS
|
Interior/Exterior Lathing
|
6/10/2014
|
Partial Approval
|
JAMES POWERS
|
Insulation
|
6/12/2014
|
Partial Approval
|
JAMES POWERS
|
Insulation
|
6/16/2014
|
Partial Approval
|
BYRON FUENTES
|
Insulation
|
6/18/2014
|
Partial Approval
|
JAMES POWERS
|
Drywall Nailing
|
6/23/2014
|
Partial Approval
|
JAMES POWERS
|
Insulation
|
6/23/2014
|
Approved
|
JAMES POWERS
|
Drywall Nailing
|
7/1/2014
|
Partial Approval
|
JAMES POWERS
|
Light Gage Steel Frame
|
7/1/2014
|
Partial Approval
|
JAMES POWERS
|
Interior/Exterior Lathing
|
7/8/2014
|
Approved
|
JAMES POWERS
|
Light Gage Steel Frame
|
7/28/2014
|
Partial Approval
|
JAMES POWERS
|
Final
|
9/22/2014
|
Not Ready for Inspection
|
JAMES POWERS
|
Footing/Foundation/Slab
|
9/22/2014
|
Approved
|
JAMES POWERS
|
Green Building Final
|
9/22/2014
|
Not Ready for Inspection
|
RICHARD DOCKUS
|
Green Building Rough
|
9/22/2014
|
Approved
|
RICHARD DOCKUS
|
Reinforced Concrete Frame
|
9/22/2014
|
Not Ready for Inspection
|
JAMES POWERS
|
Reinforced Masonry Frame
|
9/22/2014
|
Not Ready for Inspection
|
JAMES POWERS
|
SGSOV-Seismic Gas S/O Valve
|
9/22/2014
|
SGSOV Not Ready
|
JAMES POWERS
|
SUSMP-Std. Urban Storm Water
|
9/22/2014
|
Not Ready for Inspection
|
JAMES POWERS
|
Smoke Detectors
|
9/22/2014
|
Approved
|
JAMES POWERS
|
T-Bar Ceiling
|
9/22/2014
|
Approved
|
JAMES POWERS
|
Final
|
10/3/2014
|
Not Ready for Inspection
|
JAMES POWERS
|
Green Building Final
|
10/3/2014
|
Partial Inspection
|
DONALD CRICHLOW
|
Reinforced Concrete Frame
|
10/3/2014
|
Approved
|
JAMES POWERS
|
Reinforced Masonry Frame
|
10/3/2014
|
Approved
|
JAMES POWERS
|
SGSOV-Seismic Gas S/O Valve
|
10/3/2014
|
SGSOV Approved
|
JAMES POWERS
|
SUSMP-Std. Urban Storm Water
|
10/3/2014
|
Not Ready for Inspection
|
JAMES POWERS
|
T-Bar Ceiling
|
10/23/2014
|
Approved
|
JAMES POWERS
|
Green Building Final
|
12/3/2014
|
Approved
|
ROLLIN GETTLE III
|
Final
|
12/8/2014
|
OK for TCO
|
JAMES POWERS
|
SUSMP-Std. Urban Storm Water
|
12/8/2014
|
Not Ready for Inspection
|
JAMES POWERS
|
Special/Order Compliance
|
5/27/2015
|
Approved
|
JAMES POWERS
|
Final
|
6/2/2015
|
Not Ready for Inspection
|
JAMES POWERS
|
SUSMP-Std. Urban Storm Water
|
6/2/2015
|
Not Ready for Inspection
|
JAMES POWERS
|
Final
|
6/22/2015
|
OK to Issue CofO
|
JAMES POWERS
|
SUSMP-Std. Urban Storm Water
|
6/22/2015
|
Approved
|
JAMES POWERS
|