1880 N KIMBERLY LANE 90049

Certificate Information: 1880 N KIMBERLY LANE 90049

Application / Permit
07014-70000-05639
Plan Check / Job No.
B07SL02052
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO 1ST FLOOR (216 SF), 2ND FLOOR (492 SF), (N) CARPORT, AND CONVERTING GARAGE TO FAMILY ROOM (403 SF)
Permit Issued
Issued on 11/16/2007
Issuing Office
Valley
Current Status
CofO Issued on 3/19/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/8/2007 APPLICANT
Assigned to Plan Check Engineer 8/23/2007 ARMANDO MEDINA
Corrections Issued 8/25/2007 ARMANDO MEDINA
Quality Review Completed 9/21/2007 JAMESON LEE
Building Plans Picked Up 9/24/2007 APPLICANT
Applicant returned to address corrections 10/4/2007 ARMANDO MEDINA
Plan Check Approved 11/15/2007 ARMANDO MEDINA
Issued 11/16/2007 LADBS
CofO in Progress 10/12/2010 RICHARD SWETT
No Progress 10/12/2010 RICHARD SWETT
CofO in Progress 11/24/2010 RICHARD SWETT
No Progress 11/24/2010 RICHARD SWETT
CofO in Progress 3/4/2020 TIM CHRISTENSEN
Permit Finaled 3/19/2020 VINCENT COTTON
CofO Issued 3/19/2020 VINCENT COTTON
Permit Finaled 3/19/2020 VINCENT COTTON

Permit Application Clearance Information

Mailing Labels Cleared 8/9/2007 ELMER ROMERO
Eng Process Fee Ord 176,300 Cleared 10/5/2007 JAMES MORALEZ
Roof/Waste drainage to street Cleared 10/5/2007 JAMES MORALEZ
Certificate of Compliance Cleared 11/15/2007 ANDY MONTEALEGRE

Contact Information

Contractor Owner-Builder       ,
Engineer Dong, Gang; Lic. No.: C67981 6605 DE SOTO AVE 16      CANOGA PARK, CA 91303
Engineer Lieurance, Martin Ellis; Lic. No.: C54323 31129 VIA COLINAS 707      WESTLAKE VILLAGE, CA 91362

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 8/18/2007 Approved DAVID CAPTAIN
Posting Pre-Inspection 8/18/2007 Approved DAVID CAPTAIN
Grading Pre-Inspection 9/26/2007 Approved KYLE PAYNE
Deputy Drilled-In Anchors 12/5/2007 No Access for Inspection VINCENT SCIPIONI
Excavation/Setback/Form/Re-Bar 12/7/2007 Approved RICHARD MYERS
Footing/Foundation/Slab 12/7/2007 Approved RICHARD MYERS
Piling/Pier/Caisson 12/7/2007 Approved RICHARD MYERS
Footing/Foundation/Slab 12/18/2007 Approved RICHARD MYERS
PLUMBING-Rough 12/20/2007 Approved RICHARD MYERS
Floor/Roof Diaphrgm/Shear Wall 12/21/2007 Conditional Approval DAVID CHAN
Footing/Foundation/Slab 2/8/2008 No Access for Inspection DALE CARNEY
Footing/Foundation/Slab 2/11/2008 Partial Approval VINCENT SCIPIONI
BUILDING-Rough-Frame 2/19/2008 Approved RICHARD MYERS
ELECTRICAL-Rough 2/19/2008 Not Ready for Inspection RICHARD MYERS
Floor/Roof Diaphrgm/Shear Wall 2/19/2008 Approved RICHARD MYERS
PLUMBING-Rough 2/19/2008 Approved RICHARD MYERS
ELECTRICAL-Rough 2/29/2008 Approved RICHARD MYERS
Interior/Exterior Lathing 2/29/2008 Approved RICHARD MYERS
Drywall Nailing 3/7/2008 Approved DAVID CHAN
Drywall Nailing 3/10/2008 Approved RICHARD MYERS
Final 1/14/2009 Not Ready for Inspection RICHARD MYERS
SGSOV-Seismic Gas S/O Valve 1/14/2009 SGSOV Not Ready RICHARD MYERS
Service/Power Release 1/14/2009 Not Ready for Inspection RICHARD MYERS
Final 3/11/2009 Conditional Approval RICHARD MYERS
SGSOV-Seismic Gas S/O Valve 3/11/2009 SGSOV Approved RICHARD MYERS
ELECTRICAL-Final 10/7/2010 Approved RICHARD SWETT
Final 10/7/2010 Conditional Approval RICHARD SWETT
HVAC-Final 10/7/2010 Approved RICHARD SWETT
PLUMBING-Final 10/7/2010 Approved RICHARD SWETT
Final 11/24/2010 Corrections Issued RICHARD SWETT