924-928 N BAY VIEW AVE 90744

Certificate Information: 924-928 N BAY VIEW AVE 90744

Application / Permit
07014-40000-08417
Plan Check / Job No.
B07SP01649
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
2-story addition to existing single family dwelling, converting to duplex with attached garages.
Permit Issued
Issued on 3/18/2008
Issuing Office
San Pedro
Current Status
CofO Issued on 8/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2007 APPLICANT
Assigned to Plan Check Engineer 12/20/2007 TONEE THAI
Corrections Issued 1/3/2008 TONEE THAI
Quality Review Completed 1/7/2008 OLIVER ROAN
Applicant returned to address corrections 2/6/2008 TONEE THAI
Plan Check Approved 3/17/2008 TONEE THAI
Issued 3/18/2008 LADBS
CofO in Progress 8/15/2023 EUGENE CASSIDY
Permit Finaled 8/15/2023 ANSON MAGLASANG
CofO Issued 8/15/2023 ANSON MAGLASANG
Permit Finaled 8/15/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 2/11/2008 ELISEO RESURRECCION
Permit Cleared 2/11/2008 ELISEO RESURRECCION
Roof/Waste drainage to street Cleared 2/11/2008 ELISEO RESURRECCION
Eng Process Fee Ord 176,300 Cleared 2/29/2008 CHRIS TRINIDAD
Sewer availability Cleared 2/29/2008 CHRIS TRINIDAD
"Q" conditions Cleared 3/13/2008 ONDREA TYE
ZA Case Cleared 3/13/2008 ONDREA TYE
ZA Case Cleared 3/13/2008 ONDREA TYE

Contact Information

Contractor Owner-Builder       ,
Engineer Hale, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/25/2008 Corrections Issued MARVIN GODFREY
METHANE-Barrier 4/25/2008 Approved MARVIN GODFREY
METHANE-Subgrade 4/25/2008 Approved MARVIN GODFREY
Footing/Foundation/Slab 4/29/2008 Not Ready for Inspection MARVIN GODFREY
METHANE-Rough 5/6/2008 Not Ready for Inspection MARVIN GODFREY
METHANE-Subgrade 5/6/2008 Not Ready for Inspection MARVIN GODFREY
Excavation/Setback/Form/Re-Bar 5/8/2008 Approved MARVIN GODFREY
Footing/Foundation/Slab 5/8/2008 Approved MARVIN GODFREY
METHANE-Subgrade 5/8/2008 Approved MARVIN GODFREY
Floor/Roof Diaphrgm/Shear Wall 5/21/2008 Partial Approval MARVIN GODFREY
METHANE-Rough 5/21/2008 Approved MARVIN GODFREY
Wood Frame 7/8/2008 Partial Approval MARVIN GODFREY
Wood Frame 7/15/2008 Approved MARVIN GODFREY
Drywall Nailing 8/18/2010 Not Ready for Inspection MARVIN GODFREY
Final 8/18/2010 No Access for Inspection MARVIN GODFREY
SGSOV-Seismic Gas S/O Valve 8/18/2010 SGSOV Not Ready MARVIN GODFREY
Drywall Nailing 10/1/2010 Not Ready for Inspection MARVIN GODFREY
Final 10/1/2010 No Access for Inspection MARVIN GODFREY
SGSOV-Seismic Gas S/O Valve 10/1/2010 SGSOV Not Required MARVIN GODFREY
Drywall Nailing 6/20/2011 No Access for Inspection MARVIN GODFREY
Final 6/20/2011 No Access for Inspection MARVIN GODFREY
Drywall Nailing 9/2/2011 Not Ready for Inspection MARVIN GODFREY
Final 9/2/2011 Not Ready for Inspection MARVIN GODFREY
Interior/Exterior Lathing 4/16/2012 Approved MARVIN GODFREY
Insulation 8/15/2014 Approved ANSON MAGLASANG
Drywall Nailing 8/21/2014 Approved ANSON MAGLASANG
Special/Order Compliance 2/22/2016 Corrections Issued DAVID FEILER
Final 6/20/2018 Corrections Issued DAVID FEILER
Final 10/19/2021 Corrections Issued CRAIG DAVIS
Final 7/5/2022 Corrections Issued EUGENE CASSIDY
Final 5/15/2023 Not Ready for Inspection EUGENE CASSIDY
Final 6/5/2023 Corrections Issued EUGENE CASSIDY
Final 6/22/2023 Corrections Issued EUGENE CASSIDY
Final 8/2/2023 Corrections Issued EUGENE CASSIDY
Final 8/9/2023 Not Ready for Inspection EUGENE CASSIDY
Final 8/11/2023 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 8/11/2023 Approved ANSON MAGLASANG
Final 8/15/2023 OK to Issue CofO EUGENE CASSIDY
METHANE-Final 8/15/2023 Approved EUGENE CASSIDY
Smoke Detectors 8/15/2023 Approved EUGENE CASSIDY