924-928 N BAY VIEW AVE 90744
Certificate Information: 924-928 N BAY VIEW AVE 90744
- Application / Permit
- 07014-40000-08417
- Plan Check / Job No.
- B07SP01649
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- 2-story addition to existing single family dwelling, converting to duplex with attached garages.
- Permit Issued
- Issued on 3/18/2008
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 8/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/12/2007 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2007 | TONEE THAI |
| Corrections Issued | 1/3/2008 | TONEE THAI |
| Quality Review Completed | 1/7/2008 | OLIVER ROAN |
| Applicant returned to address corrections | 2/6/2008 | TONEE THAI |
| Plan Check Approved | 3/17/2008 | TONEE THAI |
| Issued | 3/18/2008 | LADBS |
| CofO in Progress | 8/15/2023 | EUGENE CASSIDY |
| Permit Finaled | 8/15/2023 | ANSON MAGLASANG |
| CofO Issued | 8/15/2023 | ANSON MAGLASANG |
| Permit Finaled | 8/15/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 2/11/2008 | ELISEO RESURRECCION |
| Permit | Cleared | 2/11/2008 | ELISEO RESURRECCION |
| Roof/Waste drainage to street | Cleared | 2/11/2008 | ELISEO RESURRECCION |
| Eng Process Fee Ord 176,300 | Cleared | 2/29/2008 | CHRIS TRINIDAD |
| Sewer availability | Cleared | 2/29/2008 | CHRIS TRINIDAD |
| "Q" conditions | Cleared | 3/13/2008 | ONDREA TYE |
| ZA Case | Cleared | 3/13/2008 | ONDREA TYE |
| ZA Case | Cleared | 3/13/2008 | ONDREA TYE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hale, Ronald Richard; Lic. No.: C17056 | 1869 PALACIOS DR SAN PEDRO, CA 90732 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/25/2008 | Corrections Issued | MARVIN GODFREY |
| METHANE-Barrier | 4/25/2008 | Approved | MARVIN GODFREY |
| METHANE-Subgrade | 4/25/2008 | Approved | MARVIN GODFREY |
| Footing/Foundation/Slab | 4/29/2008 | Not Ready for Inspection | MARVIN GODFREY |
| METHANE-Rough | 5/6/2008 | Not Ready for Inspection | MARVIN GODFREY |
| METHANE-Subgrade | 5/6/2008 | Not Ready for Inspection | MARVIN GODFREY |
| Excavation/Setback/Form/Re-Bar | 5/8/2008 | Approved | MARVIN GODFREY |
| Footing/Foundation/Slab | 5/8/2008 | Approved | MARVIN GODFREY |
| METHANE-Subgrade | 5/8/2008 | Approved | MARVIN GODFREY |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2008 | Partial Approval | MARVIN GODFREY |
| METHANE-Rough | 5/21/2008 | Approved | MARVIN GODFREY |
| Wood Frame | 7/8/2008 | Partial Approval | MARVIN GODFREY |
| Wood Frame | 7/15/2008 | Approved | MARVIN GODFREY |
| Drywall Nailing | 8/18/2010 | Not Ready for Inspection | MARVIN GODFREY |
| Final | 8/18/2010 | No Access for Inspection | MARVIN GODFREY |
| SGSOV-Seismic Gas S/O Valve | 8/18/2010 | SGSOV Not Ready | MARVIN GODFREY |
| Drywall Nailing | 10/1/2010 | Not Ready for Inspection | MARVIN GODFREY |
| Final | 10/1/2010 | No Access for Inspection | MARVIN GODFREY |
| SGSOV-Seismic Gas S/O Valve | 10/1/2010 | SGSOV Not Required | MARVIN GODFREY |
| Drywall Nailing | 6/20/2011 | No Access for Inspection | MARVIN GODFREY |
| Final | 6/20/2011 | No Access for Inspection | MARVIN GODFREY |
| Drywall Nailing | 9/2/2011 | Not Ready for Inspection | MARVIN GODFREY |
| Final | 9/2/2011 | Not Ready for Inspection | MARVIN GODFREY |
| Interior/Exterior Lathing | 4/16/2012 | Approved | MARVIN GODFREY |
| Insulation | 8/15/2014 | Approved | ANSON MAGLASANG |
| Drywall Nailing | 8/21/2014 | Approved | ANSON MAGLASANG |
| Special/Order Compliance | 2/22/2016 | Corrections Issued | DAVID FEILER |
| Final | 6/20/2018 | Corrections Issued | DAVID FEILER |
| Final | 10/19/2021 | Corrections Issued | CRAIG DAVIS |
| Final | 7/5/2022 | Corrections Issued | EUGENE CASSIDY |
| Final | 5/15/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 6/5/2023 | Corrections Issued | EUGENE CASSIDY |
| Final | 6/22/2023 | Corrections Issued | EUGENE CASSIDY |
| Final | 8/2/2023 | Corrections Issued | EUGENE CASSIDY |
| Final | 8/9/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 8/11/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2023 | Approved | ANSON MAGLASANG |
| Final | 8/15/2023 | OK to Issue CofO | EUGENE CASSIDY |
| METHANE-Final | 8/15/2023 | Approved | EUGENE CASSIDY |
| Smoke Detectors | 8/15/2023 | Approved | EUGENE CASSIDY |