10503 N BLUCHER AVE 91344
Certificate Information: 10503 N BLUCHER AVE 91344
- Application / Permit
- 07014-20002-06807
- Plan Check / Job No.
- B23VN04527
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPL. TO 07014-20000-06807 TO REVISE SCOPE OF WORK TO "ADDITON AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK PER WFPP."
- Permit Issued
- Issued on 12/15/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 2/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2023 | JESSE ARELLANO |
| Corrections Issued | 4/15/2023 | JESSE ARELLANO |
| Building Plans Picked Up | 5/1/2023 | APPLICANT |
| Applicant returned to address corrections | 8/2/2023 | ROSENDO MEDINA |
| Plan Check Approved | 12/15/2023 | ROSENDO MEDINA |
| Issued | 12/15/2023 | APPLICANT |
| Permit Finaled | 2/19/2025 | JAVIER RAMOS JR |
| Permit Finaled | 2/20/2025 | JAVIER RAMOS JR |
Permit Application Clearance Information
| Address approval | Cleared | 8/2/2023 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 8/2/2023 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 8/9/2023 | ROMAN GUTIERREZ |
| Construction near power lines | Cleared | 11/30/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/19/2024 | Approved | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 2/26/2024 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 3/1/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 3/1/2024 | Partial Inspection | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2024 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 4/10/2024 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/25/2024 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 9/25/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 9/25/2024 | Partial Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 9/25/2024 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 9/25/2024 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 9/25/2024 | Partial Approval | JAVIER RAMOS JR |
| Drywall Nailing | 10/7/2024 | Not Ready for Inspection | ROBERT GOLD |
| Insulation | 10/7/2024 | Approved | ROBERT GOLD |
| Drywall Nailing | 10/17/2024 | Approved | LOUIS ESCOTO |
| Gas Test | 11/19/2024 | Corrections Issued | MICHEL ABAJAN |
| Shower Pan | 11/19/2024 | Approved | MICHEL ABAJAN |
| Gas Test | 12/2/2024 | Not Ready for Inspection | MICHAEL CORTEZ |
| BUILDING-Rough-Frame | 1/17/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 1/17/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 1/17/2025 | Corrections Issued | JAVIER RAMOS JR |
| Gas Test | 1/17/2025 | Approved | JAVIER RAMOS JR |
| Green Building Final | 1/17/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Rough | 1/17/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 1/17/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| MERV13>=Final | 1/17/2025 | Approved | JAVIER RAMOS JR |
| MERV13>=Rough | 1/17/2025 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 1/17/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 2/19/2025 | Approved | JAVIER RAMOS JR |
| Final | 2/19/2025 | Permit Finaled | JAVIER RAMOS JR |
| Green Building Final | 2/19/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 2/19/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 2/19/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 2/19/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 2/19/2025 | Approved | JAVIER RAMOS JR |