4026 N COLLIS AVE 90032

Certificate Information: 4026 N COLLIS AVE 90032

Application / Permit
07014-10000-03281
Plan Check / Job No.
B07LA04680
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
35' X 51' TWO STORY ADDITION TO REAR OF EXISTING ONE STORY SFD, AND 24 S.F ADDITION TO EXISTING ONE STORY SFD
Permit Issued
Issued on 4/29/2009
Issuing Office
Valley
Current Status
CofO in Progress on 6/5/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/10/2007 APPLICANT
Assigned to Plan Check Engineer 6/1/2007 HERNAN ARREOLA
Corrections Issued 6/4/2007 HERNAN ARREOLA
Quality Review Completed 7/17/2007 CORA JOHNSON
Applicant returned to address corrections 4/14/2009 HERNAN ARREOLA
Plan Check Approved 4/29/2009 BARRY PESHEK
Issued 4/29/2009 LADBS
Permit Expired-Status Void 4/30/2012 TODD MALAND
Re-Activate Permit 6/6/2012 GERALD GOODMAN
CofO in Progress 6/4/2025 LILIANA PORTILLO
No Progress 6/5/2025 DEROLD HAUFF
CofO in Progress 6/5/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/20/2009 JOHN LIN
Hillside ordinance Cleared 3/20/2009 JOHN LIN
Roof/Waste drainage to street Cleared 3/20/2009 JOHN LIN
Sewer availability Cleared 3/20/2009 JOHN LIN
VHFHSZ Cleared 3/20/2009 JOSEPH JACKSON
ZI Cleared 3/20/2009 NELSON RODRIGUEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Doan, Mike H; Lic. No.: C70147 6417 KENWATER PL      WEST HILLS, CA 91307

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 5/12/2007 Approved DAVID CAPTAIN
Posting Pre-Inspection 5/12/2007 Approved DAVID CAPTAIN
Deputy Drilled-In Anchors 7/7/2009 Approved PIERRE VEGA
Footing/Foundation/Slab 7/9/2009 Corrections Issued PIERRE VEGA
Footing/Foundation/Slab 7/15/2009 Approved PIERRE VEGA
PLUMBING-Rough 8/3/2009 Not Ready for Inspection PIERRE VEGA
Rough-Elec/Plmb/HVAC 8/4/2009 Corrections Issued PIERRE VEGA
PLUMBING-Rough 8/6/2009 Conditional Approval RICHARD VENTURA
PLUMBING-Rough 8/7/2009 Partial Approval PIERRE VEGA
Footing/Foundation/Slab 8/10/2009 Approved PIERRE VEGA
Special/Order Compliance 8/25/2009 Approved PIERRE VEGA
Floor/Roof Diaphrgm/Shear Wall 10/2/2009 Approved PIERRE VEGA
Floor/Roof Diaphrgm/Shear Wall 10/9/2009 Partial Approval PIERRE VEGA
BUILDING-Rough-Frame 11/4/2009 Not Ready for Inspection PIERRE VEGA
BUILDING-Rough-Frame 11/17/2009 Not Ready for Inspection PIERRE VEGA
Rough-Elec/Plmb/HVAC 11/18/2009 Not Ready for Inspection PIERRE VEGA
Interior/Exterior Lathing 11/24/2009 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 12/16/2009 Approved PIERRE VEGA
HVAC-Rough 12/16/2009 Approved PIERRE VEGA
PLUMBING-Rough 12/16/2009 Approved PIERRE VEGA
Rough-Frame 12/16/2009 Approved PIERRE VEGA
Insulation 12/23/2009 Approved PIERRE VEGA
Drywall Nailing 1/20/2010 Approved PIERRE VEGA
BUILDING-Rough-Frame 3/4/2011 No Access for Inspection PIERRE VEGA
Final 3/4/2011 No Access for Inspection PIERRE VEGA
SGSOV-Seismic Gas S/O Valve 3/4/2011 SGSOV Not Ready PIERRE VEGA
BUILDING-Rough-Frame 6/15/2011 Not Ready for Inspection TODD MALAND
Final 6/15/2011 Not Ready for Inspection TODD MALAND
SGSOV-Seismic Gas S/O Valve 6/15/2011 SGSOV Not Ready TODD MALAND
BUILDING-Rough-Frame 6/16/2011 Approved TODD MALAND
Final 6/16/2011 Partial Inspection TODD MALAND
SGSOV-Seismic Gas S/O Valve 6/16/2011 SGSOV Approved TODD MALAND
Special/Order Compliance 6/22/2011 Partial Inspection TODD MALAND
Special/Order Compliance 7/5/2011 Order to Comply Issued TODD MALAND
Special/Order Compliance 9/8/2011 Order to Comply Issued TODD MALAND
Special/Order Compliance 9/14/2011 Order to Comply Issued TODD MALAND
Verify Sprinkler Sign Off 9/14/2011 Not Ready for Inspection TODD MALAND
Special/Order Compliance 10/27/2011 Order to Comply Issued TODD MALAND
Special/Order Compliance 1/31/2012 Partial Inspection TODD MALAND
Special/Order Compliance 4/30/2012 Permit Expired-Status Void TODD MALAND
Final 3/12/2014 No Access for Inspection WILLIAM JIMENEZ
Final 6/3/2025 OK to Issue CofO LILIANA PORTILLO
Special/Order Compliance 4/29/2026 Corrections Issued LILIANA PORTILLO
Special/Order Compliance 4/30/2026 Partial Inspection LILIANA PORTILLO