1629 N VIEWSITE DR 90069
Certificate Information: 1629 N VIEWSITE DR 90069
- Application / Permit
- 07014-10000-00881
- Plan Check / Job No.
- B07LA01290
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 252 SQ. FT. TO THE 1ST FLOOR OF EXISTING 3- STORY S.F.D. UNDER EXISTING 2- STORY PORTION AT THE DOWNHILL SLOPE, ADD NEW STAIRWAY, AND REMODEL THE EXISTING PORTION, CONVERT THE RECROOM TO THE BEDROOM SEPARATE PERMIT IS REQUIRED FOR THE GRADING WORK
- Permit Issued
- Issued on 4/25/2007
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/2/2008
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/13/2007 | APPLICANT |
| Assigned to Plan Check Engineer | 3/9/2007 | SHAHEN AKELYAN |
| Corrections Issued | 3/15/2007 | SHAHEN AKELYAN |
| Quality Review Completed | 3/16/2007 | LUIS SANCHEZ |
| Building Plans Picked Up | 3/20/2007 | APPLICANT |
| Applicant returned to address corrections | 4/5/2007 | SHAHEN AKELYAN |
| Plan Check Approved | 4/25/2007 | SHAHEN AKELYAN |
| Issued | 4/25/2007 | DWIGHT PAU |
| CofO in Progress | 7/6/2007 | BRAD BESCOS |
| CofO in Progress | 9/17/2008 | BRAD BESCOS |
| Permit Finaled | 9/25/2008 | BRADLEY NEIGHBORS |
| CofO Issued | 10/2/2008 | BRADLEY NEIGHBORS |
| Permit Finaled | 10/2/2008 | BRADLEY NEIGHBORS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/23/2007 | AVALYN KAMACHI |
| Hillside ordinance | Cleared | 3/23/2007 | IRMA HINOJOSA |
| Roof/Waste drainage to street | Cleared | 3/23/2007 | VALENTINO PUEBLOS |
| Sewer availability | Cleared | 3/23/2007 | AVALYN KAMACHI |
| Public Works-Sewers | Cleared | 3/23/2007 | AVALYN KAMACHI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Esparza, Jesus T; Lic. No.: C19990 | 6107 YORK BLVD LOS ANGELES, CA 90042 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 2/24/2007 | Approved | DAVID CAPTAIN |
| Posting Pre-Inspection | 2/24/2007 | Approved | DAVID CAPTAIN |
| BUILDING-Rough-Frame | 5/4/2007 | Partial Approval | BRAD BESCOS |
| Footing/Foundation/Slab | 5/4/2007 | Partial Approval | BRAD BESCOS |
| Footing/Foundation/Slab | 5/14/2007 | Approved | BRAD BESCOS |
| BUILDING-Rough-Frame | 5/31/2007 | Not Ready for Inspection | DEROLD HAUFF |
| BUILDING-Rough-Frame | 6/4/2007 | Approved | BRAD BESCOS |
| Drywall Nailing | 6/6/2007 | Approved | BRAD BESCOS |
| Final | 7/2/2007 | Corrections Issued | BRAD BESCOS |
| SGSOV-Seismic Gas S/O Valve | 7/2/2007 | SGSOV Approved | BRAD BESCOS |
| Final | 7/5/2007 | OK to Issue CofO | BRAD BESCOS |
| Special/Order Compliance | 5/14/2008 | Approved | BRAD BESCOS |
| Final | 5/23/2008 | Conditional Approval | BRAD BESCOS |
| Final | 6/5/2008 | Conditional Approval | BRAD BESCOS |
| Final | 6/9/2008 | Conditional Approval | BRAD BESCOS |
| Final | 9/16/2008 | OK to Issue CofO | BRAD BESCOS |