Pre-Inspection
|
1/10/2022
|
Approved
|
DAVID SANDOVAL
|
|
Deputy Drilled-In Anchors
|
2/23/2022
|
Conditional Approval
|
JESUS PINEDA
|
|
Excavation/Setback/Form/Re-Bar
|
3/10/2022
|
Not Ready for Inspection
|
DAVID SANDOVAL
|
|
Footing/Foundation/Slab
|
3/10/2022
|
Not Ready for Inspection
|
DAVID SANDOVAL
|
|
PLUMBING-Rough
|
3/10/2022
|
Not Ready for Inspection
|
DAVID SANDOVAL
|
|
Sewer
|
3/10/2022
|
Not Ready for Inspection
|
DAVID SANDOVAL
|
|
Underground Mechanical
|
3/10/2022
|
Partial Approval
|
DAVID SANDOVAL
|
|
Deputy Reinf. Concrete
|
3/15/2022
|
Partial Approval
|
DAVID SANDOVAL
|
|
Excavation/Setback/Form/Re-Bar
|
3/15/2022
|
Partial Approval
|
DAVID SANDOVAL
|
|
Footing/Foundation/Slab
|
3/15/2022
|
Partial Approval
|
DAVID SANDOVAL
|
|
Deputy Reinf. Concrete
|
3/18/2022
|
Conditional Approval
|
DAVID SANDOVAL
|
|
Deputy Other (see comments)
|
4/11/2022
|
Conditional Approval
|
JUSTIN HAWLEY
|
|
Excavation/Setback/Form/Re-Bar
|
4/11/2022
|
Partial Approval
|
SEAN HAUPT
|
|
Footing/Foundation/Slab
|
4/11/2022
|
Partial Approval
|
SEAN HAUPT
|
|
Reinforced Concrete Frame
|
4/11/2022
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Drilled-In Anchors
|
4/14/2022
|
Conditional Approval
|
KRISTEN CAUSEY
|
|
Excavation/Setback/Form/Re-Bar
|
4/19/2022
|
Partial Approval
|
DAVID SANDOVAL
|
|
Footing/Foundation/Slab
|
4/19/2022
|
Partial Approval
|
DAVID SANDOVAL
|
|
Reinforced Concrete Frame
|
4/19/2022
|
Partial Approval
|
DAVID SANDOVAL
|
|
Deputy Reinf. Concrete
|
4/20/2022
|
Conditional Approval
|
DAVID SANDOVAL
|
|
Deputy Other (see comments)
|
5/20/2022
|
Conditional Approval
|
STEVEN BACK
|
|
Deputy Drilled-In Anchors
|
5/26/2022
|
Conditional Approval
|
MORRIS JACKSON
|
|
Excavation/Setback/Form/Re-Bar
|
5/27/2022
|
Not Ready for Inspection
|
DAVID SANDOVAL
|
|
Footing/Foundation/Slab
|
5/27/2022
|
Not Ready for Inspection
|
DAVID SANDOVAL
|
|
Deputy Reinf. Concrete
|
5/31/2022
|
Conditional Approval
|
MORRIS JACKSON
|
|
Excavation/Setback/Form/Re-Bar
|
6/21/2022
|
Partial Approval
|
VINCENT HANLEY
|
|
Footing/Foundation/Slab
|
6/21/2022
|
Partial Approval
|
VINCENT HANLEY
|
|
Deputy Drilled-In Anchors
|
6/22/2022
|
Conditional Approval
|
KRISTEN CAUSEY
|
|
Deputy Reinf. Concrete
|
6/24/2022
|
Approved
|
VINCENT HANLEY
|
|
Excavation/Setback/Form/Re-Bar
|
7/5/2022
|
Approved
|
VINCENT HANLEY
|
|
Footing/Foundation/Slab
|
7/5/2022
|
Approved
|
VINCENT HANLEY
|
|
Deputy Reinf. Concrete
|
7/6/2022
|
Conditional Approval
|
MORRIS JACKSON
|
|
Deputy Drilled-In Anchors
|
10/17/2022
|
Conditional Approval
|
JESUS PINEDA
|
|
Underground Mechanical
|
10/18/2022
|
Partial Approval
|
VINCENT HANLEY
|
|
Deputy Drilled-In Anchors
|
2/22/2023
|
Approved
|
VINCENT HANLEY
|
|
Excavation/Setback/Form/Re-Bar
|
2/27/2023
|
Partial Approval
|
VINCENT HANLEY
|
|
Deputy Reinf. Concrete
|
3/3/2023
|
Approved
|
VINCENT HANLEY
|
|
BUILDING-Rough-Frame
|
9/27/2023
|
Partial Approval
|
VINCENT HANLEY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/27/2023
|
Partial Approval
|
VINCENT HANLEY
|
|
Green Building Rough
|
9/27/2023
|
Not Ready for Inspection
|
VINCENT HANLEY
|
|
MERV13>=Rough
|
9/27/2023
|
Not Ready for Inspection
|
VINCENT HANLEY
|
|
Verify Sprinkler Sign Off
|
9/27/2023
|
Not Ready for Inspection
|
VINCENT HANLEY
|
|
Wood Frame
|
9/27/2023
|
Partial Approval
|
VINCENT HANLEY
|
|
Deputy Steel/Welding
|
10/13/2023
|
Partial Approval
|
VINCENT HANLEY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/2/2023
|
Partial Approval
|
VINCENT HANLEY
|
|
Wood Frame
|
11/2/2023
|
Partial Approval
|
VINCENT HANLEY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/19/2023
|
Partial Approval
|
VINCENT HANLEY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/12/2024
|
Approved
|
VINCENT HANLEY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/5/2024
|
Partial Approval
|
THOMAS FINNILA
|
|
PLUMBING-Rough
|
11/18/2024
|
Conditional Approval
|
THOMAS FINNILA
|
|
ELECTRICAL-Rough
|
1/23/2025
|
Approved
|
SEAN WIRCH
|
|
PLUMBING-Rough
|
1/23/2025
|
Approved
|
SEAN WIRCH
|
|
Wood Frame
|
7/15/2025
|
Corrections Issued
|
THOMAS FINNILA
|