Pre-Inspection
|
5/30/2018
|
Partial Inspection
|
ROBERT DAVIS
|
|
Pre-Inspection
|
10/23/2018
|
Partial Inspection
|
ROBERT DAVIS
|
|
Pre-Inspection
|
3/4/2019
|
Partial Inspection
|
JOHN KITCKO
|
|
Grading Pre-Inspection
|
1/30/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Pre-Inspection
|
1/30/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Grading Pre-Inspection
|
2/4/2020
|
Partial Inspection
|
JOHN KITCKO
|
|
Pre-Inspection
|
2/4/2020
|
Partial Inspection
|
JOHN KITCKO
|
|
Grading Pre-Inspection
|
2/10/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Grading Pre-Inspection
|
4/28/2020
|
Partial Inspection
|
JOHN KITCKO
|
|
Deputy Other (see comments)
|
5/8/2020
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
5/11/2020
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
5/12/2020
|
Conditional Approval
|
DANIEL VARNUM
|
|
Excavation/Setback/Form/Re-Bar
|
5/26/2020
|
Conditional Approval
|
JOHN KITCKO
|
|
Deputy Reinf. Concrete
|
6/12/2020
|
Approved
|
JOHN KITCKO
|
|
Footing/Foundation/Slab
|
6/12/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Footing/Foundation/Slab
|
6/17/2020
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Footing/Foundation/Slab
|
6/18/2020
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Footing/Foundation/Slab
|
6/19/2020
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
6/25/2020
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
7/2/2020
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
7/20/2020
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
7/21/2020
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Drilled-In Anchors
|
8/3/2020
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Drilled-In Anchors
|
8/4/2020
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Steel/Welding
|
8/12/2020
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Steel/Welding
|
8/13/2020
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Steel/Welding
|
8/14/2020
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
8/18/2020
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
8/25/2020
|
Approved
|
JOHN KITCKO
|
|
Deputy Other (see comments)
|
9/15/2020
|
Approved
|
JOHN KITCKO
|
|
Deputy Other (see comments)
|
9/16/2020
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
9/17/2020
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
10/5/2020
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
10/14/2020
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
10/15/2020
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Other (see comments)
|
10/16/2020
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
10/19/2020
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
10/20/2020
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
11/19/2020
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
11/23/2020
|
Approved
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
12/1/2020
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
2/11/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Other (see comments)
|
2/25/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Other (see comments)
|
2/26/2021
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
3/1/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Other (see comments)
|
3/25/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Shotcrete
|
3/26/2021
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
4/21/2021
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
4/22/2021
|
Approved
|
ROBERT DAVIS
|
|
Deputy Other (see comments)
|
4/26/2021
|
Approved
|
JOHN KITCKO
|
|
Final
|
12/27/2021
|
Permit Finaled
|
JOHN KITCKO
|
|
Green Building Final
|
12/27/2021
|
Approved
|
JOHN KITCKO
|
|
Smoke Detectors
|
12/27/2021
|
Approved
|
JOHN KITCKO
|