Grading Pre-Inspection
|
11/28/2007
|
Partial Approval
|
TERRY HERR
|
|
Piling/Pier/Caisson
|
7/3/2013
|
Partial Approval
|
ROBERT MINASSIANS
|
|
Piling/Pier/Caisson
|
7/9/2013
|
Partial Approval
|
ROBERT MINASSIANS
|
|
Piling/Pier/Caisson
|
7/10/2013
|
Partial Approval
|
ROBERT MINASSIANS
|
|
Footing/Foundation/Slab
|
7/23/2013
|
Corrections Issued
|
ROBERT MINASSIANS
|
|
Footing/Foundation/Slab
|
7/25/2013
|
Corrections Issued
|
ROBERT MINASSIANS
|
|
Excavation/Setback/Form/Re-Bar
|
7/30/2013
|
Partial Approval
|
ROBERT MINASSIANS
|
|
Footing/Foundation/Slab
|
7/30/2013
|
Partial Approval
|
ROBERT MINASSIANS
|
|
Deputy Reinf. Concrete
|
8/1/2013
|
Approved
|
ROBERT MINASSIANS
|
|
Deputy Reinf. Concrete
|
8/2/2013
|
Approved
|
ROBERT MINASSIANS
|
|
Piling/Pier/Caisson
|
8/7/2013
|
Partial Approval
|
ROBERT MINASSIANS
|
|
Deputy Reinf. Concrete
|
8/8/2013
|
Approved
|
ROBERT MINASSIANS
|
|
Piling/Pier/Caisson
|
8/12/2013
|
Partial Approval
|
ROBERT MINASSIANS
|
|
Piling/Pier/Caisson
|
8/13/2013
|
Partial Approval
|
ROBERT MINASSIANS
|
|
Piling/Pier/Caisson
|
8/15/2013
|
Partial Approval
|
ROBERT MINASSIANS
|
|
Piling/Pier/Caisson
|
8/21/2013
|
Partial Approval
|
ROBERT MINASSIANS
|
|
Footing/Foundation/Slab
|
8/26/2013
|
Partial Approval
|
ROBERT MINASSIANS
|
|
Piling/Pier/Caisson
|
8/26/2013
|
Partial Approval
|
ROBERT MINASSIANS
|
|
Deputy Reinf. Concrete
|
8/29/2013
|
Approved
|
ROBERT MINASSIANS
|
|
Deputy Reinf. Concrete
|
9/9/2013
|
Approved
|
ROBERT MINASSIANS
|
|
Deputy Reinf. Concrete
|
9/10/2013
|
Approved
|
ROBERT MINASSIANS
|
|
Deputy Reinf. Concrete
|
9/11/2013
|
Approved
|
ROBERT MINASSIANS
|
|
Excavation/Setback/Form/Re-Bar
|
9/11/2013
|
Partial Approval
|
ROBERT MINASSIANS
|
|
Footing/Foundation/Slab
|
9/11/2013
|
Partial Approval
|
ROBERT MINASSIANS
|
|
Masonry Wall/Backfill
|
9/11/2013
|
Partial Approval
|
ROBERT MINASSIANS
|
|
Piling/Pier/Caisson
|
9/11/2013
|
Partial Approval
|
ROBERT MINASSIANS
|
|
BUILDING-Rough-Frame
|
9/12/2013
|
Not Ready for Inspection
|
ROBERT MINASSIANS
|
|
Deputy Reinf. Concrete
|
9/12/2013
|
Approved
|
ROBERT MINASSIANS
|
|
Deputy Shotcrete
|
9/12/2013
|
Approved
|
ROBERT MINASSIANS
|
|
Verify Sprinkler Sign Off
|
9/12/2013
|
Not Ready for Inspection
|
ROBERT MINASSIANS
|
|
Deputy Reinf. Concrete
|
9/13/2013
|
Approved
|
ROBERT MINASSIANS
|
|
Deputy Reinf. Concrete
|
9/16/2013
|
Approved
|
DOMINIC DANERI
|
|
Deputy Shotcrete
|
9/16/2013
|
Approved
|
DOMINIC DANERI
|
|
Footing/Foundation/Slab
|
9/16/2013
|
Partial Approval
|
DOMINIC DANERI
|
|
Deputy Reinf. Concrete
|
9/17/2013
|
Approved
|
ROBERT MINASSIANS
|
|
Deputy Shotcrete
|
9/17/2013
|
Approved
|
ROBERT MINASSIANS
|
|
Deputy Reinf. Concrete
|
9/18/2013
|
Approved
|
ROBERT MINASSIANS
|
|
Deputy Shotcrete
|
9/18/2013
|
Approved
|
ROBERT MINASSIANS
|
|
Deputy Reinf. Concrete
|
9/19/2013
|
Approved
|
ROBERT MINASSIANS
|
|
Deputy Shotcrete
|
9/19/2013
|
Approved
|
ROBERT MINASSIANS
|
|
Deputy Reinf. Concrete
|
9/20/2013
|
Approved
|
ROBERT MINASSIANS
|
|
Deputy Shotcrete
|
9/20/2013
|
Approved
|
ROBERT MINASSIANS
|
|
Footing/Foundation/Slab
|
9/20/2013
|
Partial Approval
|
ROBERT MINASSIANS
|
|
Masonry Wall/Backfill
|
9/20/2013
|
Partial Approval
|
ROBERT MINASSIANS
|
|
Piling/Pier/Caisson
|
9/20/2013
|
Partial Approval
|
ROBERT MINASSIANS
|
|
Deputy Reinf. Concrete
|
9/24/2013
|
Approved
|
ROBERT MINASSIANS
|
|
Deputy Reinf. Concrete
|
9/25/2013
|
Approved
|
ROBERT MINASSIANS
|
|
Deputy Reinf. Concrete
|
9/26/2013
|
Approved
|
ROBERT MINASSIANS
|
|
Footing/Foundation/Slab
|
9/26/2013
|
Partial Approval
|
ROBERT MINASSIANS
|
|
Deputy Reinf. Concrete
|
9/27/2013
|
Approved
|
ROBERT MINASSIANS
|
|
Deputy Shotcrete
|
9/30/2013
|
Approved
|
ROBERT MINASSIANS
|
|
Deputy Shotcrete
|
10/7/2013
|
Approved
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
10/7/2013
|
Partial Approval
|
RAUL BARAJAS
|
|
Deputy Shotcrete
|
10/8/2013
|
Approved
|
RAUL BARAJAS
|
|
Deputy Shotcrete
|
10/9/2013
|
Approved
|
RAUL BARAJAS
|
|
Deputy Shotcrete
|
10/10/2013
|
Approved
|
RAUL BARAJAS
|
|
Deputy Shotcrete
|
10/11/2013
|
Approved
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
10/11/2013
|
Partial Approval
|
RAUL BARAJAS
|
|
BUILDING-Rough-Frame
|
10/16/2013
|
Partial Approval
|
DOMINIC DANERI
|
|
Verify Sprinkler Sign Off
|
10/16/2013
|
Not Ready for Inspection
|
DOMINIC DANERI
|
|
Footing/Foundation/Slab
|
10/28/2013
|
Partial Approval
|
ROBERT MINASSIANS
|
|
Masonry Wall/Backfill
|
10/28/2013
|
Partial Approval
|
ROBERT MINASSIANS
|
|
Footing/Foundation/Slab
|
11/19/2013
|
Partial Approval
|
ROBERT MINASSIANS
|
|
Masonry Wall/Backfill
|
11/19/2013
|
Partial Approval
|
ROBERT MINASSIANS
|
|
Footing/Foundation/Slab
|
12/17/2013
|
Partial Approval
|
ENRIQUE MIRELES
|
|
Piling/Pier/Caisson
|
12/30/2013
|
Approved
|
RAUL BARAJAS
|
|
Piling/Pier/Caisson
|
1/3/2014
|
Approved
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
1/8/2014
|
Partial Approval
|
ENRIQUE MIRELES
|
|
Footing/Foundation/Slab
|
1/10/2014
|
Partial Approval
|
ENRIQUE MIRELES
|
|
Footing/Foundation/Slab
|
1/29/2014
|
Partial Approval
|
RAUL BARAJAS
|
|
Footing/Foundation/Slab
|
2/11/2014
|
Partial Approval
|
RUBEN SALAS
|
|
Footing/Foundation/Slab
|
2/20/2014
|
Not Ready for Inspection
|
RUBEN SALAS
|
|
Footing/Foundation/Slab
|
2/21/2014
|
Partial Approval
|
RAUL BARAJAS
|
|
Verify Sprinkler Sign Off
|
2/21/2014
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Deputy Reinf. Concrete
|
3/3/2014
|
Approved
|
DOMINIC DANERI
|
|
PLUMBING-Rough
|
3/13/2014
|
Partial Approval
|
PIERRE VEGA
|
|
Footing/Foundation/Slab
|
4/1/2014
|
Partial Approval
|
PIERRE VEGA
|
|
Footing/Foundation/Slab
|
4/29/2014
|
Not Ready for Inspection
|
PIERRE VEGA
|
|
Footing/Foundation/Slab
|
4/30/2014
|
Partial Approval
|
PIERRE VEGA
|
|
Verify Sprinkler Sign Off
|
4/30/2014
|
Not Ready for Inspection
|
PIERRE VEGA
|
|
Footing/Foundation/Slab
|
5/5/2014
|
Partial Approval
|
PIERRE VEGA
|
|
Footing/Foundation/Slab
|
5/20/2014
|
Partial Approval
|
PIERRE VEGA
|
|
Footing/Foundation/Slab
|
5/28/2014
|
Partial Approval
|
PIERRE VEGA
|
|
Footing/Foundation/Slab
|
6/9/2014
|
Not Ready for Inspection
|
PIERRE VEGA
|
|
Footing/Foundation/Slab
|
6/10/2014
|
Order to Comply Issued
|
PIERRE VEGA
|
|
Verify Sprinkler Sign Off
|
6/10/2014
|
Not Ready for Inspection
|
PIERRE VEGA
|
|
Footing/Foundation/Slab
|
6/26/2014
|
Approved
|
PIERRE VEGA
|
|
BUILDING-Rough-Frame
|
7/3/2014
|
Not Ready for Inspection
|
PIERRE VEGA
|
|
Verify Sprinkler Sign Off
|
7/3/2014
|
Not Ready for Inspection
|
PIERRE VEGA
|
|
Masonry Wall/Backfill
|
7/11/2014
|
Partial Approval
|
PIERRE VEGA
|
|
Verify Sprinkler Sign Off
|
7/11/2014
|
Not Ready for Inspection
|
PIERRE VEGA
|
|
Masonry Wall/Backfill
|
7/30/2014
|
Approved
|
RAUL BARAJAS
|
|
Verify Sprinkler Sign Off
|
7/30/2014
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
BUILDING-Rough-Frame
|
9/17/2014
|
Not Ready for Inspection
|
PIERRE VEGA
|
|
Verify Sprinkler Sign Off
|
9/17/2014
|
Not Ready for Inspection
|
PIERRE VEGA
|
|
BUILDING-Rough-Frame
|
9/22/2014
|
Not Ready for Inspection
|
PIERRE VEGA
|
|
Verify Sprinkler Sign Off
|
9/22/2014
|
Not Ready for Inspection
|
PIERRE VEGA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/24/2014
|
Partial Approval
|
PIERRE VEGA
|
|
Verify Sprinkler Sign Off
|
9/24/2014
|
Not Ready for Inspection
|
PIERRE VEGA
|
|
Footing/Foundation/Slab
|
10/6/2014
|
Partial Approval
|
PIERRE VEGA
|
|
Verify Sprinkler Sign Off
|
10/6/2014
|
Not Ready for Inspection
|
PIERRE VEGA
|
|
Masonry Wall/Backfill
|
10/22/2014
|
Partial Approval
|
PIERRE VEGA
|
|
Verify Sprinkler Sign Off
|
10/22/2014
|
Not Ready for Inspection
|
PIERRE VEGA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/27/2015
|
Approved
|
PIERRE VEGA
|
|
Verify Sprinkler Sign Off
|
1/27/2015
|
No Access for Inspection
|
PIERRE VEGA
|
|
Sewer
|
2/25/2015
|
Order to Comply Issued
|
PIERRE VEGA
|
|
PLUMBING-Rough
|
3/9/2015
|
Partial Inspection
|
PIERRE VEGA
|
|
HVAC-Rough
|
5/18/2015
|
Partial Approval
|
PIERRE VEGA
|
|
PLUMBING-Rough
|
5/27/2015
|
Not Ready for Inspection
|
PIERRE VEGA
|
|
PLUMBING-Rough
|
5/28/2015
|
Not Ready for Inspection
|
PIERRE VEGA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/2/2015
|
Conditional Approval
|
RAUL BARAJAS
|
|
HVAC-Rough
|
6/2/2015
|
Partial Inspection
|
RAUL BARAJAS
|
|
PLUMBING-Rough
|
6/2/2015
|
Partial Inspection
|
RAUL BARAJAS
|
|
Verify Sprinkler Sign Off
|
6/2/2015
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
PLUMBING-Rough
|
6/11/2015
|
Partial Approval
|
RUBEN SALAS
|
|
Interior/Exterior Lathing
|
6/29/2015
|
Partial Approval
|
RAUL BARAJAS
|
|
ELECTRICAL-Rough
|
7/17/2015
|
Partial Approval
|
RAUL BARAJAS
|
|
Interior/Exterior Lathing
|
7/23/2015
|
Partial Approval
|
RAUL BARAJAS
|
|
Verify Sprinkler Sign Off
|
7/23/2015
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
BUILDING-Rough-Frame
|
8/31/2015
|
Partial Inspection
|
RAUL BARAJAS
|
|
Verify Sprinkler Sign Off
|
8/31/2015
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Interior/Exterior Lathing
|
9/16/2015
|
Partial Inspection
|
RAUL BARAJAS
|
|
Insulation
|
9/24/2015
|
No Access for Inspection
|
RUBEN SALAS
|
|
Drywall Nailing
|
9/29/2015
|
Partial Approval
|
RAUL BARAJAS
|
|
Insulation
|
9/29/2015
|
Approved
|
RAUL BARAJAS
|
|
Rough-Elec/Plmb/HVAC
|
9/29/2015
|
Partial Approval
|
RAUL BARAJAS
|
|
Insulation
|
12/14/2015
|
Not Ready for Inspection
|
TIMOTHY O CONNER
|
|
Insulation
|
1/14/2016
|
Partial Approval
|
RAUL BARAJAS
|
|
Drywall Nailing
|
1/25/2016
|
Not Ready for Inspection
|
TIMOTHY O CONNER
|
|
BUILDING-Rough-Frame
|
1/27/2016
|
Not Ready for Inspection
|
TIMOTHY O CONNER
|
|
Verify Sprinkler Sign Off
|
1/27/2016
|
Approved
|
TIMOTHY O CONNER
|
|
BUILDING-Rough-Frame
|
1/29/2016
|
Approved
|
RAUL BARAJAS
|
|
Drywall Nailing
|
2/2/2016
|
Partial Approval
|
RAUL BARAJAS
|
|
Insulation
|
2/2/2016
|
Approved
|
RAUL BARAJAS
|
|
Interior/Exterior Lathing
|
2/2/2016
|
Partial Approval
|
RAUL BARAJAS
|
|
Drywall Nailing
|
2/3/2016
|
Partial Approval
|
TIMOTHY O CONNER
|
|
Interior/Exterior Lathing
|
2/4/2016
|
Partial Approval
|
TIMOTHY O CONNER
|
|
Interior/Exterior Lathing
|
8/4/2016
|
Approved
|
RAUL BARAJAS
|
|
Drywall Nailing
|
8/5/2016
|
Approved
|
RAUL BARAJAS
|
|
PLUMBING-Rough
|
3/24/2017
|
Approved
|
RONALD COWAN
|
|
Sewer
|
3/24/2017
|
Approved
|
RONALD COWAN
|
|
Final
|
12/21/2017
|
Not Ready for Inspection
|
CRAIG VAUGHAN
|
|
Footing/Foundation/Slab
|
12/21/2017
|
Not Ready for Inspection
|
CRAIG VAUGHAN
|
|
SGSOV-Seismic Gas S/O Valve
|
12/21/2017
|
SGSOV Not Ready
|
CRAIG VAUGHAN
|
|
Smoke Detectors
|
12/21/2017
|
Not Ready for Inspection
|
CRAIG VAUGHAN
|
|
ELECTRICAL-Final
|
1/15/2019
|
Partial Inspection
|
DANNY TOLENTINO
|
|
ELECTRICAL-Final
|
8/26/2019
|
No Access for Inspection
|
RICHARD STEINBACH
|
|
PLUMBING-Final
|
8/26/2019
|
No Access for Inspection
|
RICHARD STEINBACH
|
|
ELECTRICAL-Final
|
8/27/2019
|
Approved
|
RICHARD STEINBACH
|
|
PLUMBING-Final
|
8/27/2019
|
Corrections Issued
|
RICHARD STEINBACH
|
|
HVAC-Final
|
8/28/2019
|
Corrections Issued
|
RICHARD STEINBACH
|
|
PLUMBING-Final
|
8/28/2019
|
Approved
|
RICHARD STEINBACH
|
|
HVAC-Final
|
9/4/2019
|
Corrections Issued
|
RAUL BARAJAS
|
|
HVAC-Final
|
9/18/2019
|
Corrections Issued
|
RICHARD STEINBACH
|
|
HVAC-Final
|
10/1/2019
|
Approved
|
RICHARD STEINBACH
|
|
Final
|
6/8/2020
|
Corrections Issued
|
JOSEPH MCGARRY
|
|
Footing/Foundation/Slab
|
6/8/2020
|
Approved
|
JOSEPH MCGARRY
|
|
SGSOV-Seismic Gas S/O Valve
|
6/8/2020
|
SGSOV Not Ready
|
JOSEPH MCGARRY
|
|
Smoke Detectors
|
6/8/2020
|
Approved
|
JOSEPH MCGARRY
|
|
Special/Order Compliance
|
4/23/2026
|
Permit Expired-Status Void
|
BRIAN SULLIVAN
|
|
Pre-Inspection
|
7/14/2026
|
Permit Expired
|
BRIAN SULLIVAN
|
|
Special/Order Compliance
|
7/14/2026
|
Corrections Issued
|
BRIAN SULLIVAN
|