1677 S VICTORIA AVE 90019
Certificate Information: 1677 S VICTORIA AVE 90019
- Application / Permit
- 07010-10000-04355
- Plan Check / Job No.
- B07LA10713
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Carport
- Work Description
- Proposed 2- car carport in front of house and interior remodel of 1st and 2nd floor kitchen remodel, stair relocation, master bedroom add N) bathrrom & walkincloset, replace DRY rot lumber and damage roof.
- Permit Issued
- Issued on 1/22/2008
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/17/2007 | APPLICANT |
| Assigned to Plan Check Engineer | 10/25/2007 | SALVADOR QUINTANILLA |
| Corrections Issued | 10/27/2007 | SALVADOR QUINTANILLA |
| Quality Review Completed | 11/19/2007 | VICTOR CUEVAS |
| Building Plans Picked Up | 11/20/2007 | APPLICANT |
| Applicant returned to address corrections | 12/31/2007 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 1/10/2008 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 1/16/2008 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 1/17/2008 | SALVADOR QUINTANILLA |
| Plan Check Approved | 1/22/2008 | SALVADOR QUINTANILLA |
| Issued | 1/22/2008 | SALVADOR QUINTANILLA |
| CofO in Progress | 3/2/2026 | JUSTIN HAWLEY |
| Permit Finaled | 3/3/2026 | DEROLD HAUFF |
| CofO Issued | 3/3/2026 | DEROLD HAUFF |
| Permit Finaled | 3/3/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 11/20/2007 | LISA COOKE |
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2008 | CHRISTINE CHANG |
| HPOZ | Cleared | 1/17/2008 | CRAIG WEBER |
| Roof/Waste drainage to street | Cleared | 1/17/2008 | CHRISTINE CHANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke, Conway Cecil; Lic. No.: S1597 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 1/30/2008 | Corrections Issued | MANUEL TEJADA |
| METHANE-Rough | 1/31/2008 | Not Ready for Inspection | MANUEL TEJADA |
| Footing/Foundation/Slab | 2/15/2008 | Partial Inspection | RONALD MYRICK |
| METHANE-Barrier | 2/15/2008 | Not Ready for Inspection | RONALD MYRICK |
| METHANE-Subgrade | 2/15/2008 | Not Ready for Inspection | RONALD MYRICK |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2008 | Partial Approval | RONALD MYRICK |
| Rough-Frame | 3/24/2008 | Corrections Issued | ALAN CHRISTENSEN |
| ELECTRICAL-Rough | 3/28/2008 | Not Ready for Inspection | RONALD MYRICK |
| Gas Test | 3/28/2008 | Not Ready for Inspection | RONALD MYRICK |
| HVAC-Rough | 3/28/2008 | Not Ready for Inspection | RONALD MYRICK |
| PLUMBING-Rough | 3/28/2008 | Not Ready for Inspection | RONALD MYRICK |
| Rough-Frame | 3/28/2008 | Not Ready for Inspection | RONALD MYRICK |
| BUILDING-Rough-Frame | 4/4/2008 | Corrections Issued | RONALD MYRICK |
| Rough-Elec/Plmb/HVAC | 5/19/2008 | Not Ready for Inspection | RONALD MYRICK |
| Rough-Frame | 5/19/2008 | Not Ready for Inspection | RONALD MYRICK |
| BUILDING-Rough-Frame | 5/30/2008 | Not Ready for Inspection | RONALD MYRICK |
| METHANE-Rough | 5/30/2008 | Not Ready for Inspection | RONALD MYRICK |
| ELECTRICAL-Rough | 7/7/2008 | Not Ready for Inspection | RONALD MYRICK |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2008 | Not Ready for Inspection | RONALD MYRICK |
| Gas Test | 7/7/2008 | Not Ready for Inspection | RONALD MYRICK |
| HVAC-Rough | 7/7/2008 | Not Ready for Inspection | RONALD MYRICK |
| METHANE-Rough | 7/7/2008 | Not Ready for Inspection | RONALD MYRICK |
| PLUMBING-Rough | 7/7/2008 | Not Ready for Inspection | RONALD MYRICK |
| Rough-Frame | 7/7/2008 | Not Ready for Inspection | RONALD MYRICK |
| ELECTRICAL-Rough | 7/8/2008 | Partial Approval | RONALD MYRICK |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2008 | Not Ready for Inspection | RONALD MYRICK |
| HVAC-Rough | 7/8/2008 | Partial Approval | RONALD MYRICK |
| METHANE-Rough | 7/8/2008 | Approved | RONALD MYRICK |
| PLUMBING-Rough | 7/8/2008 | Approved | RONALD MYRICK |
| Rough-Frame | 7/8/2008 | Not Ready for Inspection | RONALD MYRICK |
| BUILDING-Rough-Frame | 7/18/2008 | Not Ready for Inspection | RONALD MYRICK |
| Rough-Frame | 7/22/2008 | Not Ready for Inspection | RONALD MYRICK |
| Interior/Exterior Lathing | 7/25/2008 | Not Ready for Inspection | RONALD MYRICK |
| Rough-Frame | 7/25/2008 | Not Ready for Inspection | RONALD MYRICK |
| Rough-Frame | 7/29/2008 | Approved | RONALD MYRICK |
| Rough-Elec/Plmb/HVAC | 8/8/2008 | Partial Approval | CHET TODD |
| Rough-Elec/Plmb/HVAC | 8/12/2008 | Approved | RONALD MYRICK |
| Drywall Nailing | 8/18/2008 | Approved | RONALD MYRICK |
| Interior/Exterior Lathing | 8/18/2008 | Approved | RONALD MYRICK |
| Special/Order Compliance | 6/4/2009 | Partial Inspection | GREGORY VOLPE |
| BUILDING-Rough-Frame | 10/27/2010 | Approved | CARL LOCKRIDGE |
| Final | 10/27/2010 | No Access for Inspection | CARL LOCKRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2010 | Approved | CARL LOCKRIDGE |
| Footing/Foundation/Slab | 10/27/2010 | Approved | CARL LOCKRIDGE |
| METHANE-Barrier | 10/27/2010 | Approved | CARL LOCKRIDGE |
| METHANE-Subgrade | 10/27/2010 | Approved | CARL LOCKRIDGE |
| SGSOV-Seismic Gas S/O Valve | 10/27/2010 | SGSOV Approved | CARL LOCKRIDGE |
| Final | 4/13/2012 | No Access for Inspection | WILLIAM JIMENEZ |
| Final | 4/4/2016 | Corrections Issued | SCOTT FINNILA |
| Final | 1/12/2018 | Not Ready for Inspection | SALVADOR GONZALEZ |
| Final | 2/2/2026 | Corrections Issued | JUSTIN HAWLEY |
| Final | 3/2/2026 | OK to Issue CofO | JUSTIN HAWLEY |