1037 S VICTORIA AVE 90019
Certificate Information: 1037 S VICTORIA AVE 90019
- Application / Permit
- 07010-10000-01589
- Plan Check / Job No.
- B07LA03803
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- (N) GARAGE & RECREATION ROOM, 2-STORY.
- Permit Issued
- Issued on 6/8/2007
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/16/2007 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2007 | BOK GOH |
| Corrections Issued | 4/29/2007 | BOK GOH |
| Quality Review Completed | 5/1/2007 | EDITA MATTIS |
| Building Plans Picked Up | 5/9/2007 | APPLICANT |
| Plan Check Approved | 6/6/2007 | BOK GOH |
| Issued | 6/8/2007 | DWIGHT PAU |
| CofO in Progress | 9/9/2020 | ARTHUR SARGSYAN |
| No Progress | 10/9/2020 | ARTHUR SARGSYAN |
| CofO in Progress | 3/23/2021 | JOSEPH MCGARRY |
| Permit Finaled | 6/3/2021 | DEROLD HAUFF |
| CofO Issued | 6/3/2021 | DEROLD HAUFF |
| Permit Finaled | 6/3/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2007 | WESLEY TANIJIRI |
| Roof/Waste drainage to street | Cleared | 6/6/2007 | WESLEY TANIJIRI |
| Sewer availability | Cleared | 6/6/2007 | WESLEY TANIJIRI |
| Public Works-Highway Ded. | Cleared | 6/6/2007 | WESLEY TANIJIRI |
| Public Works-Open Permits | Cleared | 6/6/2007 | WESLEY TANIJIRI |
| Public Works-Sewers | Cleared | 6/6/2007 | WESLEY TANIJIRI |
Contact Information
| Contractor | Paul & Clara Construction; Lic. No.: 627822-B | 9335 LUBEC STREET DOWNEY, CA 90240 |
| Engineer | Chi, Chi-Wol; Lic. No.: C53156 | 19623 BOMAR CT ROWLAND HEIGHTS, CA 91748 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/14/2007 | Corrections Issued | RONALD COWAN |
| Footing/Foundation/Slab | 6/15/2007 | Not Ready for Inspection | RONALD COWAN |
| Special/Order Compliance | 7/13/2007 | Approved | RONALD COWAN |
| BUILDING-Rough-Frame | 8/15/2007 | Conditional Approval | RONALD COWAN |
| Insulation | 9/7/2007 | Approved | LUIS BARRALES |
| Interior/Exterior Lathing | 9/7/2007 | Corrections Issued | LUIS BARRALES |
| Drywall Nailing | 9/20/2007 | Approved | NICHOLAS PARISI |
| Interior/Exterior Lathing | 9/27/2007 | Approved | LUIS BARRALES |
| Final | 1/28/2008 | Corrections Issued | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 1/28/2008 | SGSOV Not Ready | RONALD COWAN |
| Final | 10/22/2009 | Partial Approval | ALAN CHRISTENSEN |
| Final | 1/11/2010 | Not Ready for Inspection | WILLIAM MITCHELL |
| Final | 1/14/2010 | No Access for Inspection | WILLIAM MITCHELL |
| Final | 2/17/2012 | Not Ready for Inspection | GARY KERR |
| Final | 5/15/2018 | Not Ready for Inspection | JOSEPH MCGARRY |
| Final | 8/19/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Final | 9/9/2020 | OK to Issue CofO | ARTHUR SARGSYAN |
| Special/Order Compliance | 10/8/2020 | Corrections Issued | ARTHUR SARGSYAN |
| Final | 12/2/2020 | Corrections Issued | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 1/20/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Final | 3/12/2021 | Corrections Issued | JOSEPH MCGARRY |
| Final | 3/23/2021 | OK to Issue CofO | JOSEPH MCGARRY |