1 S BEVERLY RIDGE TER 90210

Certificate Information: 1 S BEVERLY RIDGE TER 90210

Application / Permit
06043-30000-00369
Plan Check / Job No.
M06WL00081
Group
Mechanical
Type
Fire Sprinkler
Sub-Type
1 or 2 Family Dwelling
Primary Use
()
Work Description
INSTALL ONE HUNDRED AND EIGHTEEN (118) NEW AUTOMATIC FIRE SPRINKLER HEADS IN A SINGLE FAMILY DWELLING. A 2" WATER METER SHALL BE INSTALLED ON INCOMING DOMESTIC WATER ERVICE LINE.
Permit Issued
Issued on 2/3/2006
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 6/1/2007

Permit Application Status History

Submitted 2/3/2006 APPLICANT
Assigned to Plan Check Engineer 2/3/2006 YOGEN THAKAR
Issued 2/3/2006 KERMIT YOUNG
Permit Finaled 5/31/2007 THOMAS COWAN

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Flame Master Fire Protection; Lic. No.: 834551-C16 7319 OAK PARK AVENUE      VAN NUYS, CA 91406

Inspector Information

STANLEY IZUMI, (213) 482-9585 Office Hours: 7:00-8:00 AM MON-FRI
WILLEM FELDER, (213) 482-9585 Office Hours: 7:00-8:00 AM MON-FRI
GUADALUPE TOLEDO, (213) 482-9585 Office Hours: 7:00-8:00 AM MON-FRI
VICENTE DIAZ, (213) 482-9585 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Overhead 4/4/2006 Corrections Issued KARIN IZUMI
Overhead Hydro 4/4/2006 Corrections Issued KARIN IZUMI
Rough 4/4/2006 Corrections Issued KARIN IZUMI
Final 5/19/2006 Corrections Issued KARIN IZUMI
Overhead 5/19/2006 Corrections Issued KARIN IZUMI
Overhead Hydro 5/19/2006 Corrections Issued KARIN IZUMI
Rough 5/19/2006 Corrections Issued KARIN IZUMI
Overhead 6/27/2006 Not Ready for Inspection KARIN IZUMI
Overhead Hydro 6/27/2006 Not Ready for Inspection KARIN IZUMI
Rough 6/27/2006 Not Ready for Inspection KARIN IZUMI
Fire Department Connection 7/19/2006 Not Ready for Inspection KARIN IZUMI
Overhead 7/19/2006 Not Ready for Inspection KARIN IZUMI
Overhead Hydro 7/19/2006 Corrections Issued KARIN IZUMI
Rough 7/19/2006 Corrections Issued KARIN IZUMI
Final 4/27/2007 Corrections Issued KARIN IZUMI
Final 4/27/2007 Corrections Issued THOMAS COWAN
Overhead 4/27/2007 Corrections Issued KARIN IZUMI
Overhead 4/27/2007 Corrections Issued THOMAS COWAN
Overhead Hydro 4/27/2007 Corrections Issued KARIN IZUMI
Overhead Hydro 4/27/2007 Corrections Issued THOMAS COWAN
Rough 4/27/2007 Corrections Issued KARIN IZUMI
Rough 4/27/2007 Corrections Issued THOMAS COWAN
Underground Flush 5/11/2007 Corrections Issued KARIN IZUMI
Underground Hydro 5/11/2007 Corrections Issued KARIN IZUMI
Underground Flush 5/17/2007 Corrections Issued KARIN IZUMI
Underground Hydro 5/17/2007 Corrections Issued KARIN IZUMI
Final 5/31/2007 Permit Finaled THOMAS COWAN