4150 N VAN HORNE AVE 90032
Certificate Information: 4150 N VAN HORNE AVE 90032
- Application / Permit
- 06010-10000-00265
- Plan Check / Job No.
- B06LA00638
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Carport
- Work Description
- PROPOSED NEW TWO CAR CARPORT @ REAR OF LOT.
- Permit Issued
- Issued on 1/24/2006
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/24/2006 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2006 | EDITA MATTIS |
| Corrections Issued | 1/24/2006 | EDITA MATTIS |
| Plan Check Approved | 1/24/2006 | EDITA MATTIS |
| Plan Check Approved | 1/24/2006 | EDITA MATTIS |
| Issued | 1/24/2006 | ERWIN LEE |
| CofO in Progress | 6/9/2025 | LILIANA PORTILLO |
| Permit Finaled | 6/10/2025 | DEROLD HAUFF |
| CofO Issued | 6/10/2025 | DEROLD HAUFF |
| Permit Finaled | 6/10/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2006 | ILDEFONSO DELACRUZ |
| Roof/Waste drainage to street | Cleared | 1/24/2006 | ILDEFONSO DELACRUZ |
Contact Information
| No Data Available. |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/23/2006 | Corrections Issued | DOMINIC DANERI |
| Rough-Elec/Plmb/HVAC | 5/9/2006 | Corrections Issued | DOMINIC DANERI |
| Final | 11/16/2006 | Conditional Approval | PIERRE VEGA |
| Final | 10/27/2008 | Conditional Approval | PIERRE VEGA |
| Final | 11/24/2008 | No Access for Inspection | PIERRE VEGA |
| Special/Order Compliance | 1/28/2009 | Approved | PIERRE VEGA |
| Special/Order Compliance | 7/15/2009 | No Access for Inspection | PIERRE VEGA |
| Special/Order Compliance | 10/19/2009 | No Access for Inspection | PIERRE VEGA |
| Final | 3/15/2010 | Conditional Approval | PIERRE VEGA |
| Final | 3/16/2010 | Conditional Approval | ENRIQUE MIRELES |
| Final | 8/24/2011 | Partial Inspection | TODD MALAND |
| Special/Order Compliance | 9/23/2011 | Partial Inspection | TODD MALAND |
| Special/Order Compliance | 10/26/2011 | Partial Inspection | TODD MALAND |
| Special/Order Compliance | 10/27/2011 | Order to Comply Issued | TODD MALAND |
| Final | 12/4/2018 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 6/3/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 6/6/2025 | OK to Issue CofO | LILIANA PORTILLO |