1749 W CHANDELEUR DR 90732

Certificate Information: 1749 W CHANDELEUR DR 90732

Application / Permit
05014-40000-09041
Plan Check / Job No.
B05SP01126
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-STORY ADDITION & MAJOR RENOVATION OF EXIST'G RESIDENCE. Related Elec., Hvac., & Plumb.
Permit Issued
Issued on 1/12/2006
Issuing Office
San Pedro
Current Status
Issued on 1/12/2006
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/13/2005 APPLICANT
Assigned to Plan Check Engineer 9/30/2005 TAI VU
Corrections Issued 11/3/2005 TAI VU
Quality Review Completed 11/7/2005 OLIVER ROAN
Applicant returned to address corrections 12/6/2005 FRANCISCO ROJAS
Plan Check Approved 12/23/2005 FRANCISCO ROJAS
Issued 1/12/2006 RODNEY DUNCAN
Permit Expired-Status Void 5/2/2013 MARK HATFIELD
Re-Activate Permit 6/3/2013 MARK HATFIELD
Permit Expired-Status Void 9/22/2016 PAUL BECKER
Re-Activate Permit 12/23/2020 PAUL BECKER

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/7/2005 MATT HENDRIX
Hillside ordinance Cleared 11/7/2005 MATT HENDRIX
Hillside ordinance Cleared 11/7/2005 MATT HENDRIX
Hillside ordinance Cleared 11/7/2005 MATT HENDRIX
Roof/Waste drainage to street Cleared 11/7/2005 MATT HENDRIX
Sewer availability Cleared 11/7/2005 MATT HENDRIX
Grading Pre-Inspection Cleared 11/30/2005 TAI VU

Contact Information

Contractor Owner-Builder       ,
Engineer Hale, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 5/31/2006 Corrections Issued MARK HATFIELD
Special/Order Compliance 6/1/2006 Partial Inspection PETER BARMUS
Footing/Foundation/Slab 6/20/2006 Corrections Issued MARK HATFIELD
Rough-Elec/Plmb/HVAC 6/20/2006 Corrections Issued MARK HATFIELD
ELECTRICAL-Rough 6/23/2006 Partial Approval MARK HATFIELD
Footing/Foundation/Slab 6/23/2006 Approved MARK HATFIELD
PLUMBING-Rough 6/23/2006 Partial Approval MARK HATFIELD
BUILDING-Rough-Frame 7/19/2006 Partial Approval MARK HATFIELD
ELECTRICAL-Rough 7/19/2006 Partial Approval MARK HATFIELD
PLUMBING-Rough 7/19/2006 Partial Approval MARK HATFIELD
Footing/Foundation/Slab 7/27/2006 Corrections Issued MARK HATFIELD
Footing/Foundation/Slab 7/28/2006 Approved JEFF NAPIER
Rough-Frame 9/11/2006 Partial Approval MARK HATFIELD
Deputy Drilled-In Anchors 9/15/2006 Partial Approval MARK HATFIELD
BUILDING-Rough-Frame 10/16/2006 Partial Inspection MARK HATFIELD
BUILDING-Rough-Frame 12/6/2006 Corrections Issued MARK HATFIELD
ELECTRICAL-Rough 1/29/2007 Not Ready for Inspection MARK HATFIELD
HVAC-Rough 1/29/2007 Not Ready for Inspection MARK HATFIELD
PLUMBING-Rough 1/29/2007 Not Ready for Inspection MARK HATFIELD
BUILDING-Rough-Frame 4/25/2007 Corrections Issued MARK HATFIELD
ELECTRICAL-Rough 4/25/2007 Corrections Issued MARK HATFIELD
HVAC-Rough 4/25/2007 Approved MARK HATFIELD
PLUMBING-Rough 4/25/2007 Corrections Issued MARK HATFIELD
Interior/Exterior Lathing 5/23/2007 Corrections Issued MARK HATFIELD
PLUMBING-Rough 5/23/2007 Not Ready for Inspection MARK HATFIELD
BUILDING-Rough-Frame 5/25/2007 Approved MARK HATFIELD
Interior/Exterior Lathing 5/25/2007 Approved MARK HATFIELD
PLUMBING-Rough 5/25/2007 Approved MARK HATFIELD
Insulation 7/3/2007 Approved DAVID ROBERTS
Drywall Nailing 7/31/2007 No Access for Inspection MARK HATFIELD
Final 2/1/2008 Partial Inspection MARK HATFIELD
Final 10/19/2009 Corrections Issued SERGIO RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 10/19/2009 SGSOV Not Ready SERGIO RODRIGUEZ
Smoke Detectors 10/19/2009 Not Ready for Inspection SERGIO RODRIGUEZ
Final 3/10/2010 No Access for Inspection SERGIO RODRIGUEZ
Final 12/23/2011 Partial Inspection MARK HATFIELD
Final 8/22/2012 Corrections Issued MARK HATFIELD
Special/Order Compliance 5/1/2013 Permit Expired-Status Void MARK HATFIELD
Special/Order Compliance 2/4/2015 Corrections Issued ANSON MAGLASANG
SWPPP-Const. Storm Water 1/7/2016 Completed ANSON MAGLASANG
Special/Order Compliance 9/22/2016 Not Ready for Inspection PAUL BECKER