1402 E CRUCES ST 90744

Certificate Information: 1402 E CRUCES ST 90744

Application / Permit
05014-40000-02942
Plan Check / Job No.
B05SP00178
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-STORY ADDITION (Add 5 Bed Rooms, 1 Den, 1 Family Room, 3.5 Bath Rooms, 1 Storage, & 2-Car Garage) & MAJOR REMODEL TO EXIST'G RESIDENCE. Related Elec., Hvac., & Plumb.
Permit Issued
Issued on 7/6/2005
Issuing Office
San Pedro
Current Status
Issued on 7/6/2005
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/7/2005 TAI VU
Fees Due 4/7/2005 TAI VU
Submitted 4/7/2005 RODNEY DUNCAN
Assigned to Plan Check Engineer 5/18/2005 TAI VU
Corrections Issued 5/18/2005 TAI VU
Reviewed by Supervisor 5/18/2005 OLIVER ROAN
Plan Check Approved 7/6/2005 TAI VU
Issued 7/6/2005 RODNEY DUNCAN
Permit Expired-Status Void 5/26/2010 MARVIN GODFREY
Re-Activate Permit 8/23/2012 MARVIN GODFREY

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/6/2005 REMBERTO JAVIER
Roof/Waste drainage to street Cleared 7/6/2005 REMBERTO JAVIER
Sewer availability Cleared 7/6/2005 REMBERTO JAVIER

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke, Conway Cecil; Lic. No.: S1597 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/4/2006 Approved DAVID ROBERTS
Underground Mechanical 1/4/2006 Approved DAVID ROBERTS
Footing/Foundation/Slab 1/12/2006 Approved DAVID ROBERTS
BUILDING-Rough-Frame 8/3/2007 Partial Approval MARVIN GODFREY
Final 3/18/2009 No Access for Inspection MARVIN GODFREY
Final 5/5/2009 Corrections Issued MARVIN GODFREY
Final 1/8/2010 No Access for Inspection MARVIN GODFREY
Final 1/12/2010 Not Ready for Inspection MARVIN GODFREY
Special/Order Compliance 5/26/2010 Permit Expired-Status Void MARVIN GODFREY
Special/Order Compliance 5/29/2014 Corrections Issued ANSON MAGLASANG
BUILDING-Rough-Frame 10/24/2016 Corrections Issued DAVID FEILER
ELECTRICAL-Rough 10/24/2016 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 10/24/2016 Not Ready for Inspection DAVID FEILER
Special/Order Compliance 7/13/2017 Corrections Issued DAVID FEILER
Interior/Exterior Lathing 12/20/2021 Corrections Issued JOHN KLARIN
Interior/Exterior Lathing 1/3/2022 Corrections Issued JOHN KLARIN