1915 N APEX AVE 90039

Certificate Information: 1915 N APEX AVE 90039

Application / Permit
05014-20000-09546
Plan Check / Job No.
B05VN20808
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Add 20'-10"x20'-4" one-story family room addition to existing 2-story, 3-unit apartment building per engineered plans.
Permit Issued
Issued on 1/11/2006
Issuing Office
Metro
Current Status
CofO Issued on 1/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/27/2005 APPLICANT
Assigned to Plan Check Engineer 10/7/2005 EDDIE YAMAMOTO
Corrections Issued 10/9/2005 EDDIE YAMAMOTO
Quality Review Completed 10/21/2005 NICHOLAS TROTTA
Building Plans Picked Up 10/25/2005 APPLICANT
Applicant returned to address corrections 12/2/2005 EDDIE YAMAMOTO
Plan Check Approved 12/20/2005 EDDIE YAMAMOTO
Issued 1/11/2006 PRECY SANCHEZ
CofO in Progress 12/21/2022 JONATHAN QUACH
CofO Issued 1/11/2023 TED RIES
Permit Finaled 1/11/2023 TED RIES

Permit Application Clearance Information

DAS Clearance Cleared 10/1/2005 ALDOUS CHIC
Housing rent stabilization Cleared 12/13/2005 PETER PARTNOFF
Grading Pre-Inspection Cleared 12/20/2005 EDDIE YAMAMOTO

Contact Information

Contractor Owner-Builder       ,
Engineer Steinberg, Raymond Earl; Lic. No.: S1936 12053 STEWARTON DR      NORTHRIDGE, CA 91324

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/24/2006 Corrections Issued JEFFREY CHRISTIAN
Footing/Foundation/Slab 1/27/2006 Approved JEFFREY CHRISTIAN
Rough-Frame 2/3/2006 Partial Inspection JEFFREY CHRISTIAN
Rough-Frame 2/7/2006 Partial Inspection JEFFREY CHRISTIAN
Rough-Frame 2/8/2006 Partial Inspection JEFFREY CHRISTIAN
Rough-Frame 2/10/2006 Conditional Approval JEFFREY CHRISTIAN
Rough-Frame 2/13/2006 Partial Inspection JEFFREY CHRISTIAN
Insulation 2/28/2006 Not Ready for Inspection JEFFREY CHRISTIAN
Interior/Exterior Lathing 2/28/2006 Not Ready for Inspection JEFFREY CHRISTIAN
Interior/Exterior Lathing 3/6/2006 Corrections Issued JEFFREY CHRISTIAN
Insulation 3/9/2006 Approved JEFFREY CHRISTIAN
Rough-Frame 3/16/2006 Conditional Approval JEFFREY CHRISTIAN
Rough-Frame 3/20/2006 Approved JEFFREY CHRISTIAN
Rough-Frame 3/28/2006 Partial Inspection JEFFREY CHRISTIAN
Interior/Exterior Lathing 4/7/2006 Corrections Issued JEFFREY CHRISTIAN
Interior/Exterior Lathing 4/10/2006 Approved JEFFREY CHRISTIAN
Rough-Frame 4/13/2006 Partial Inspection JEFFREY CHRISTIAN
Drywall Nailing 4/27/2006 Corrections Issued JEFFREY CHRISTIAN
Rough-Frame 4/28/2006 Partial Inspection JEFFREY CHRISTIAN
Final 3/10/2010 Corrections Issued JONATHAN ALLEN
Final 8/12/2020 Partial Inspection EDWIN GREGORYONA
Final 6/17/2022 Corrections Issued JONATHAN QUACH
Pre-Inspection 11/10/2022 Corrections Issued JONATHAN QUACH
Final 12/5/2022 Not Ready for Inspection JONATHAN QUACH
Final 12/14/2022 Partial Inspection JONATHAN QUACH
Final 12/21/2022 OK to Issue CofO JONATHAN QUACH