2401 N YORKSHIRE DR 90065
Certificate Information: 2401 N YORKSHIRE DR 90065
- Application / Permit
- 05010-10000-04056
- Plan Check / Job No.
- B05LA12531
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SFD WITH ATTACHED GARAGE AND ELEVATED FRONT ACCESS AND DRIVEWAY
- Permit Issued
- Issued on 9/27/2007
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 3/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/8/2005 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2005 | TONEE THAI |
| Corrections Issued | 8/17/2005 | TONEE THAI |
| Quality Review Completed | 8/26/2005 | BILL STUTSMAN |
| Applicant returned to address corrections | 4/3/2006 | TONEE THAI |
| Applicant returned to address corrections | 9/27/2006 | TONEE THAI |
| Applicant returned to address corrections | 10/23/2006 | TONEE THAI |
| Applicant returned to address corrections | 12/12/2006 | TONEE THAI |
| Applicant returned to address corrections | 5/25/2007 | TONEE THAI |
| Applicant returned to address corrections | 9/13/2007 | TONEE THAI |
| Plan Check Approved | 9/27/2007 | TONEE THAI |
| Issued | 9/27/2007 | LADBS |
| CofO in Progress | 3/12/2024 | HAMIK HARTOUNIAN |
| CofO Issued | 3/19/2024 | DEROLD HAUFF |
| Permit Finaled | 3/19/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Specific Plan | Cleared | 4/25/2006 | JAMES ANGUIANO |
| A-Permit | Cleared | 5/26/2006 | DANIEL SUE |
| Address approval | Cleared | 5/26/2006 | DAVID CHIN |
| Hillside ordinance | Cleared | 5/26/2006 | DANIEL SUE |
| Hillside ordinance | Cleared | 5/26/2006 | DANIEL SUE |
| Hillside ordinance | Cleared | 5/26/2006 | DANIEL SUE |
| Hillside ordinance | Cleared | 5/26/2006 | DANIEL SUE |
| Miscellaneous | Cleared | 5/26/2006 | DANIEL SUE |
| Roof/Waste drainage to street | Cleared | 5/26/2006 | DANIEL SUE |
| Sewer availability | Cleared | 5/26/2006 | VALENTINO PUEBLOS |
| Eng Process Fee Ord 176,300 | Cleared | 9/12/2006 | VALENTINO PUEBLOS |
| ZA Case | Cleared | 9/13/2006 | NICHOLAS BROWN |
| Stormwater Pollution Mitigatn | Cleared | 9/18/2006 | AYZA JACKSON |
| Encroachment in public way | Cleared | 9/20/2006 | JASON CHANG |
| Miscellaneous | Cleared | 4/12/2007 | JASON CHANG |
| ZA Case | Cleared | 7/5/2007 | NICHOLAS BROWN |
| Miscellaneous | Cleared | 9/25/2007 | PAUL MULLIS |
Contact Information
| Engineer | Espino, Manuel A; Lic. No.: C55526 | 17302 DE GROOT PL CERRITOS, CA 90703 |
| Engineer | Yang, Jane-Fu Jeff; Lic. No.: GE2344 | 13728 CARLETON DR CERRITOS, CA 90703 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Posting Pre-Inspection | 8/24/2005 | Approved | STEVE WEIS |
| Pre-Inspection | 10/15/2007 | Approved | TODD MALAND |
| Deputy Reinf. Concrete | 10/30/2007 | Approved | TODD MALAND |
| Deputy Reinf. Concrete | 11/8/2007 | Approved | TODD MALAND |
| Piling/Pier/Caisson | 11/9/2007 | Approved | TODD MALAND |
| Footing/Foundation/Slab | 11/21/2007 | Approved | TODD MALAND |
| Footing/Foundation/Slab | 12/5/2007 | Partial Approval | CHARLES FARRELL |
| Footing/Foundation/Slab | 3/6/2008 | Partial Approval | ERNEST MARKHAM |
| Deputy Reinf. Concrete | 3/7/2008 | Approved | TODD MALAND |
| Footing/Foundation/Slab | 3/24/2008 | Partial Approval | TODD MALAND |
| Deputy Reinf. Concrete | 3/27/2008 | Approved | TODD MALAND |
| Deputy Steel/Welding | 4/22/2008 | Approved | TODD MALAND |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2008 | Partial Approval | TODD MALAND |
| Deputy Steel/Welding | 5/21/2008 | Approved | TODD MALAND |
| Deputy Steel/Welding | 6/19/2008 | Approved | TODD MALAND |
| Rough-Frame | 7/15/2008 | Partial Approval | TODD MALAND |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2008 | Approved | TODD MALAND |
| Rough-Frame | 9/8/2008 | Approved | TODD MALAND |
| Insulation | 9/11/2008 | Approved | TODD MALAND |
| Drywall Nailing | 9/17/2008 | Approved | CHARLES FARRELL |
| Interior/Exterior Lathing | 9/17/2008 | Not Ready for Inspection | CHARLES FARRELL |
| Interior/Exterior Lathing | 10/2/2008 | Approved | TODD MALAND |
| Special/Order Compliance | 9/22/2009 | Order to Comply Issued | TODD MALAND |
| Final | 1/17/2012 | Not Ready for Inspection | TODD MALAND |
| Final | 3/20/2012 | No Access for Inspection | RONALD COWAN |
| Special/Order Compliance | 5/19/2015 | Approved | RONALD COWAN |
| Footing/Foundation/Slab | 12/29/2017 | Approved | LUIS ALVAREZ |
| Final | 1/10/2020 | Partial Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 4/27/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Gas Test | 4/27/2022 | Approved | HAMIK HARTOUNIAN |
| HVAC-Final | 4/27/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Final | 4/27/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 2/12/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 2/12/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Final | 2/12/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Final | 2/12/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Service/Power Release | 2/12/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Final | 3/1/2024 | Approved | HAMIK HARTOUNIAN |
| Final | 3/1/2024 | Partial Inspection | HAMIK HARTOUNIAN |
| HVAC-Final | 3/1/2024 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 3/1/2024 | Approved | HAMIK HARTOUNIAN |
| Service/Power Release | 3/1/2024 | Approved | HAMIK HARTOUNIAN |
| Final | 3/12/2024 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Service/Power Release | 3/12/2024 | Approved | HAMIK HARTOUNIAN |