860 N FAIRFAX AVE 90046
Certificate Information: 860 N FAIRFAX AVE 90046
- Application / Permit
- 04014-10000-01801
- Plan Check / Job No.
- B04LA00462
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- 1-story, 15' x 23' (330 sqft) addition to (E) Restaurant.
- Permit Issued
- Issued on 12/20/2004
- Issuing Office
- Metro
- Current Status
- Issued on 12/20/2004
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Fees Due | 3/4/2004 | GEORGE KUC |
| Fees Due | 3/4/2004 | JULIO ZAFRA |
| Submitted | 3/4/2004 | DWIGHT PAU |
| PC Assigned | 3/12/2004 | TIMOTHY FAN |
| Corrections Issued | 3/15/2004 | TIMOTHY FAN |
| Reviewed by Supervisor | 3/16/2004 | JOHN VASQUEZ |
| Issued | 12/20/2004 | BOSCO TANG |
Permit Application Clearance Information
| Highway dedication | Cleared | 11/12/2004 | GARY LAM |
| Roof/Waste drainage to street | Cleared | 11/12/2004 | JUAN GONZAGA |
| Sewer availability | Cleared | 11/12/2004 | JUAN GONZAGA |
| DAS Clearance | Cleared | 12/17/2004 | EDDIE GARIN |
| Food establishment approval | Cleared | 12/17/2004 | LACDHS APPROVED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hanbali, Amjad Moh'D; Lic. No.: C42213 | 1334 EAST PALMDALE BLVD SUITE F PALMDALE, CA 93550 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/12/2005 | Corrections Issued | MICHAEL DICKSON |
| Footing/Foundation/Slab | 4/15/2005 | Approved | MICHAEL DICKSON |
| Rough-Frame | 6/7/2005 | Approved | MICHAEL DICKSON |
| Interior/Exterior Lathing | 6/17/2005 | Approved | TODD ROBERTSON |
| Final | 9/22/2005 | Conditional Approval | TODD ROBERTSON |
| Final | 3/3/2009 | Corrections Issued | MICHAEL DICKSON |
| Final | 3/16/2009 | Corrections Issued | MICHAEL DICKSON |
| Final | 5/4/2011 | Corrections Issued | MICHAEL DICKSON |
| Final | 6/1/2011 | Conditional Approval | MICHAEL DICKSON |
| Final | 3/19/2026 | Partial Inspection | CHRISTOPHER BLACKWOOD |
| Pre-Inspection | 4/13/2026 | Corrections Issued | CHRISTOPHER BLACKWOOD |
| Final | 4/16/2026 | Not Ready for Inspection | MARTIN TAVITIAN |
| Final | 7/9/2026 | Not Ready for Inspection | IAN BLINN |