1 S BEVERLY RIDGE TER 90210
Certificate Information: 1 S BEVERLY RIDGE TER 90210
- Application / Permit
- 04010-30001-01948
- Plan Check / Job No.
- B05WL00532
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPP TO PCIS # 04010-30000-01948 TO REVISE FLOOR PLANS AND TOTAL SQ FOOTAGE FOR NEW SFD/GARAGE
- Permit Issued
- Issued on 6/29/2005
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 10/12/2007
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Fees Due | 4/27/2005 | NORLITO MEDRANO |
| Submitted | 4/27/2005 | APPLICANT |
| Submitted | 4/27/2005 | KERMIT YOUNG |
| Pre-Insp Completed | 4/28/2005 | RANDALL KINA |
| Assigned to Plan Check Engineer | 4/28/2005 | RANDELL KINA |
| PC Assigned | 4/28/2005 | RANDALL KINA |
| Corrections Issued | 5/3/2005 | RANDALL KINA |
| Corrections Issued | 5/3/2005 | RANDELL KINA |
| Reviewed by Supervisor | 5/3/2005 | REBECCA CAWYER |
| Plan Check Approved | 6/29/2005 | RANDALL KINA |
| Issued | 6/29/2005 | KERMIT YOUNG |
| Permit Finaled | 10/11/2007 | DEROLD HAUFF |
Permit Application Clearance Information
| Design Review Board approval | Cleared | 5/24/2005 | SEVANA MAILIAN |
| Specific Plan | Cleared | 5/24/2005 | SEVANA MAILIAN |
| Grading Pre-Inspection | Cleared | 6/28/2005 | RANDALL KINA |
| Eng Process Fee Ord 176,300 | Cleared | 6/29/2005 | FELICIANO REYES |
| Hillside ordinance | Cleared | 6/29/2005 | FELICIANO REYES |
| Hillside ordinance | Cleared | 6/29/2005 | FELICIANO REYES |
| Hillside ordinance | Cleared | 6/29/2005 | FELICIANO REYES |
| Sewer availability | Cleared | 6/29/2005 | RACHEL BASS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Berkoz, Ertunga; Lic. No.: S2504 | 3106 PENNEY DR SIMI VALLEY, CA 93063 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/9/2006 | Approved | DEROLD HAUFF |
| Footing/Foundation/Slab | 2/1/2006 | Partial Approval | DEROLD HAUFF |
| Final | 9/26/2007 | Not Ready for Inspection | DEROLD HAUFF |
| Final | 10/4/2007 | Not Ready for Inspection | DEROLD HAUFF |
| Final | 10/10/2007 | Not Ready for Inspection | DEROLD HAUFF |
| Final | 10/11/2007 | Permit Finaled | DEROLD HAUFF |