11001 N WINNETKA AVE 91311
Certificate Information: 11001 N WINNETKA AVE 91311
- Application / Permit
- 02014-20000-07246
- Plan Check / Job No.
- --
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- ADD BEDROOM,BATHROOM,LAUNDRY & ENTRY(+891 SQ. FT.),ATTACHED PATIO COVER(7'9" X 15'2") & ATTACHED ONE CAR GARAGE(13' X 22'2") TO EXISTING ACCESSORY LIVING QUARTERS.(No kitchen facilities).
- Permit Issued
- Issued on 4/15/2003
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 5/14/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Fees Due | 10/25/2002 | SULASTRI TJIA |
| Submitted | 10/25/2002 | BOSCO TANG |
| PC Assigned | 11/1/2002 | HARLEN CARRAHER |
| Corrections Issued | 11/1/2002 | HARLEN CARRAHER |
| Issued | 4/15/2003 | DWIGHT PAU |
| Permit Expired-Status Void | 12/22/2009 | ERWIN LARRANAGA |
| Re-Activate Permit | 5/16/2013 | ELMER BLAND |
| CofO in Progress | 5/14/2026 | JACK KARGODORIAN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/1/2002 | HARLEN CARRAHER |
| Hillside ordinance | Cleared | 11/1/2002 | JOHN LIN |
| Mailing Labels | Cleared | 11/1/2002 | HARLEN CARRAHER |
| Miscellaneous | Cleared | 11/1/2002 | JAIME LOPEZ |
| Miscellaneous | Cleared | 11/1/2002 | JAIME LOPEZ |
| ZA Case | Cleared | 11/1/2002 | JAIME LOPEZ |
| ZA Case | Cleared | 11/1/2002 | JAIME LOPEZ |
| Sewer availability | Cleared | 11/13/2002 | LLOYD TAGGART |
| Private sewage disp. approval | Cleared | 4/15/2003 | HARLEN CARRAHER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou, Dawn Renee; Lic. No.: C52361 | 5810 SERRANIA AVENUE WOODLAND HILLS, CA 91367 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 10/29/2002 | Approved | KEVIN PORTER |
| Posting Pre-Inspection | 10/29/2002 | Approved | KEVIN PORTER |
| Excavation/Setback/Form/Re-Bar | 4/23/2003 | Conditional Approval | CHARLES BOGHOSKHAN |
| Footing/Foundation/Slab | 4/23/2003 | Conditional Approval | CHARLES BOGHOSKHAN |
| Excavation/Setback/Form/Re-Bar | 4/24/2003 | Approved | CHARLES BOGHOSKHAN |
| Footing/Foundation/Slab | 4/24/2003 | Approved | CHARLES BOGHOSKHAN |
| Excavation/Setback/Form/Re-Bar | 4/28/2003 | Corrections Issued | CHARLES BOGHOSKHAN |
| Footing/Foundation/Slab | 4/28/2003 | Corrections Issued | CHARLES BOGHOSKHAN |
| Underground Mechanical | 4/28/2003 | Corrections Issued | CHARLES BOGHOSKHAN |
| Excavation/Setback/Form/Re-Bar | 5/1/2003 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| Footing/Foundation/Slab | 5/1/2003 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| Underground Mechanical | 5/1/2003 | Corrections Issued | CHARLES BOGHOSKHAN |
| Excavation/Setback/Form/Re-Bar | 5/9/2003 | No Access for Inspection | CHARLES BOGHOSKHAN |
| Footing/Foundation/Slab | 5/9/2003 | No Access for Inspection | CHARLES BOGHOSKHAN |
| Underground Mechanical | 5/9/2003 | No Access for Inspection | CHARLES BOGHOSKHAN |
| Excavation/Setback/Form/Re-Bar | 5/13/2003 | Corrections Issued | CHARLES BOGHOSKHAN |
| Footing/Foundation/Slab | 5/13/2003 | Corrections Issued | CHARLES BOGHOSKHAN |
| Underground Mechanical | 5/13/2003 | Corrections Issued | CHARLES BOGHOSKHAN |
| Excavation/Setback/Form/Re-Bar | 5/14/2003 | Conditional Approval | CHARLES BOGHOSKHAN |
| Footing/Foundation/Slab | 5/14/2003 | Conditional Approval | CHARLES BOGHOSKHAN |
| Underground Mechanical | 5/14/2003 | Conditional Approval | CHARLES BOGHOSKHAN |
| Footing/Foundation/Slab | 6/16/2003 | Corrections Issued | CHARLES BOGHOSKHAN |
| Excavation/Setback/Form/Re-Bar | 6/25/2003 | Approved | CHARLES BOGHOSKHAN |
| Footing/Foundation/Slab | 6/25/2003 | Approved | CHARLES BOGHOSKHAN |
| HVAC-Rough | 6/25/2003 | Approved | CHARLES BOGHOSKHAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2003 | Conditional Approval | CHARLES BOGHOSKHAN |
| ELECTRICAL-Rough | 7/11/2003 | Corrections Issued | CHARLES BOGHOSKHAN |
| PLUMBING-Rough | 7/11/2003 | Corrections Issued | CHARLES BOGHOSKHAN |
| BUILDING-Rough-Frame | 7/18/2003 | Corrections Issued | CHARLES BOGHOSKHAN |
| ELECTRICAL-Rough | 7/18/2003 | Corrections Issued | CHARLES BOGHOSKHAN |
| HVAC-Rough | 7/18/2003 | Corrections Issued | CHARLES BOGHOSKHAN |
| PLUMBING-Rough | 7/18/2003 | Corrections Issued | CHARLES BOGHOSKHAN |
| BUILDING-Rough-Frame | 7/22/2003 | Corrections Issued | CHARLES BOGHOSKHAN |
| ELECTRICAL-Rough | 7/22/2003 | Corrections Issued | CHARLES BOGHOSKHAN |
| HVAC-Rough | 7/22/2003 | Corrections Issued | CHARLES BOGHOSKHAN |
| PLUMBING-Rough | 7/22/2003 | Corrections Issued | CHARLES BOGHOSKHAN |
| BUILDING-Rough-Frame | 7/28/2003 | Approved | CHARLES BOGHOSKHAN |
| ELECTRICAL-Rough | 7/28/2003 | Conditional Approval | CHARLES BOGHOSKHAN |
| HVAC-Rough | 7/28/2003 | Approved | CHARLES BOGHOSKHAN |
| PLUMBING-Rough | 7/28/2003 | Conditional Approval | CHARLES BOGHOSKHAN |
| Insulation | 7/30/2003 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 7/31/2003 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| Drywall Nailing | 8/5/2003 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 8/5/2003 | Approved | CHARLES BOGHOSKHAN |
| Final-COMBINATION | 9/3/2003 | Corrections Issued | CHARLES BOGHOSKHAN |
| SGSOV-Seismic Gas S/O Valve | 9/3/2003 | Corrections Issued | CHARLES BOGHOSKHAN |
| Final-COMBINATION | 9/18/2003 | Conditional Approval | CHARLES BOGHOSKHAN |
| SGSOV-Seismic Gas S/O Valve | 9/18/2003 | SGSOV Approved | CHARLES BOGHOSKHAN |
| Final-COMBINATION | 9/19/2003 | Conditional Approval | CHARLES BOGHOSKHAN |
| SGSOV-Seismic Gas S/O Valve | 9/19/2003 | SGSOV Approved | CHARLES BOGHOSKHAN |
| Final | 4/29/2008 | No Access for Inspection | ERWIN LARRANAGA |
| Special/Order Compliance | 9/10/2008 | No Access for Inspection | ERWIN LARRANAGA |
| ELECTRICAL-Final | 12/22/2008 | Approved | ERWIN LARRANAGA |
| Final | 12/22/2008 | Conditional Approval | ERWIN LARRANAGA |
| HVAC-Final | 12/22/2008 | Approved | ERWIN LARRANAGA |
| PLUMBING-Final | 12/22/2008 | Approved | ERWIN LARRANAGA |
| Special/Order Compliance | 12/22/2008 | Partial Inspection | JOHN KENNEDY |
| Special/Order Compliance | 12/22/2009 | Permit Expired-Status Void | ERWIN LARRANAGA |
| Final | 5/17/2013 | Corrections Issued | LUIS BARRALES |
| Final | 3/26/2026 | Corrections Issued | JACK KARGODORIAN |
| Pre-Inspection | 4/9/2026 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 5/13/2026 | OK to Issue CofO | JACK KARGODORIAN |