1839 W 49TH ST 90062
Certificate Information: 1839 W 49TH ST 90062
- Application / Permit
- 02010-10000-02504
- Plan Check / Job No.
- --
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- New 1-story, 40' x 25' IRR. shaped (898 sqft) 2-car garage and recreation room at rear of lot per city standard. All related electrical and plumbing works.
- Permit Issued
- Issued on 7/23/2002
- Issuing Office
- Metro
- Current Status
- CofO in Progress on 6/5/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| PC Fees Due | 7/22/2002 | JANENE COX |
| PC Fees Paid | 7/22/2002 | MAXX SKOULPHONG |
| Issued | 7/23/2002 | MAXX SKOULPHONG |
| Permit Expired-Status Void | 2/11/2026 | JOHN PARKER |
| Re-Activate Permit | 2/21/2026 | JOHN PARKER |
| CofO in Progress | 6/5/2026 | SABAS ALONSO |
Permit Application Clearance Information
| Sewer availability | Cleared | 7/22/2002 | JOSE HERNANDEZ |
Contact Information
| Contractor | Givens Eric; Lic. No.: 449841-B | 1508 S VICTORIA AVE LOS ANGELES, CA 90019 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/30/2002 | Approved | ROBERT MCDOWELL |
| Rough-Elec/Plmb/HVAC | 12/30/2002 | Approved | DAVID CAPTAIN |
| Rough-Elec/Plmb/HVAC | 2/3/2003 | Approved | ROBERT MCDOWELL |
| Rough-Frame | 2/3/2003 | Approved | ROBERT MCDOWELL |
| Insulation | 3/5/2003 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 3/5/2003 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 3/18/2003 | Approved | ROBERT MCDOWELL |
| Final | 5/2/2003 | OK to Issue CofO | ROBERT MCDOWELL |
| ELECTRICAL-Final | 4/15/2008 | No Access for Inspection | FELIPE PENICHE |
| Final | 4/15/2008 | Not Ready for Inspection | FELIPE PENICHE |
| Gas Test | 4/15/2008 | No Access for Inspection | FELIPE PENICHE |
| HVAC-Final | 4/15/2008 | No Access for Inspection | FELIPE PENICHE |
| PLUMBING-Final | 4/15/2008 | No Access for Inspection | FELIPE PENICHE |
| SGSOV-Seismic Gas S/O Valve | 4/15/2008 | SGSOV Not Ready | FELIPE PENICHE |
| Final | 9/10/2008 | Not Ready for Inspection | ROBERT MCDOWELL |
| Final | 7/17/2024 | Corrections Issued | DAVID FEILER |
| Pre-Inspection | 7/23/2024 | Corrections Issued | MICHAEL LEWIS |
| Pre-Inspection | 7/25/2024 | Corrections Issued | JOSE MACIAS |
| Pre-Inspection | 8/1/2024 | Corrections Issued | ANTHONY EGSON |
| Pre-Inspection | 2/11/2026 | Not Ready for Inspection | JOHN PARKER |
| Final | 2/24/2026 | Corrections Issued | SABAS ALONSO |
| Final | 3/6/2026 | Corrections Issued | BARRY HACHE |
| Final | 6/4/2026 | OK to Issue CofO | SABAS ALONSO |
| Pre-Inspection | 6/4/2026 | Conditional Approval | SABAS ALONSO |