1839 W 49TH ST 90062

Certificate Information: 1839 W 49TH ST 90062

Application / Permit
02010-10000-02504
Plan Check / Job No.
--
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
New 1-story, 40' x 25' IRR. shaped (898 sqft) 2-car garage and recreation room at rear of lot per city standard. All related electrical and plumbing works.
Permit Issued
Issued on 7/23/2002
Issuing Office
Metro
Current Status
CofO in Progress on 6/5/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

PC Fees Due 7/22/2002 JANENE COX
PC Fees Paid 7/22/2002 MAXX SKOULPHONG
Issued 7/23/2002 MAXX SKOULPHONG
Permit Expired-Status Void 2/11/2026 JOHN PARKER
Re-Activate Permit 2/21/2026 JOHN PARKER
CofO in Progress 6/5/2026 SABAS ALONSO

Permit Application Clearance Information

Sewer availability Cleared 7/22/2002 JOSE HERNANDEZ

Contact Information

Contractor Givens Eric; Lic. No.: 449841-B 1508 S VICTORIA AVE      LOS ANGELES, CA 90019

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/30/2002 Approved ROBERT MCDOWELL
Rough-Elec/Plmb/HVAC 12/30/2002 Approved DAVID CAPTAIN
Rough-Elec/Plmb/HVAC 2/3/2003 Approved ROBERT MCDOWELL
Rough-Frame 2/3/2003 Approved ROBERT MCDOWELL
Insulation 3/5/2003 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 3/5/2003 Approved ROBERT MCDOWELL
Drywall Nailing 3/18/2003 Approved ROBERT MCDOWELL
Final 5/2/2003 OK to Issue CofO ROBERT MCDOWELL
ELECTRICAL-Final 4/15/2008 No Access for Inspection FELIPE PENICHE
Final 4/15/2008 Not Ready for Inspection FELIPE PENICHE
Gas Test 4/15/2008 No Access for Inspection FELIPE PENICHE
HVAC-Final 4/15/2008 No Access for Inspection FELIPE PENICHE
PLUMBING-Final 4/15/2008 No Access for Inspection FELIPE PENICHE
SGSOV-Seismic Gas S/O Valve 4/15/2008 SGSOV Not Ready FELIPE PENICHE
Final 9/10/2008 Not Ready for Inspection ROBERT MCDOWELL
Final 7/17/2024 Corrections Issued DAVID FEILER
Pre-Inspection 7/23/2024 Corrections Issued MICHAEL LEWIS
Pre-Inspection 7/25/2024 Corrections Issued JOSE MACIAS
Pre-Inspection 8/1/2024 Corrections Issued ANTHONY EGSON
Pre-Inspection 2/11/2026 Not Ready for Inspection JOHN PARKER
Final 2/24/2026 Corrections Issued SABAS ALONSO
Final 3/6/2026 Corrections Issued BARRY HACHE
Final 6/4/2026 OK to Issue CofO SABAS ALONSO
Pre-Inspection 6/4/2026 Conditional Approval SABAS ALONSO