6100 N TOPANGA CANYON BLVD SUITE 1300 91367
Certificate Information: 6100 N TOPANGA CANYON BLVD SUITE 1300 91367
- Application / Permit
- 01016-20000-09095
- Plan Check / Job No.
- B01VN00712
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- T.I. OF EXISTING 50000 SQ FT RETAIL SPACE 1300 WITHIN EXIST MALL.
- Permit Issued
- Issued on 6/28/2001
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 6/24/2002
Permit Application Status History
Fees Due | 5/18/2001 | SULASTRI TJIA |
Submitted | 5/18/2001 | TONI ZANOTTI |
PC Assigned | 5/25/2001 | DOUG NAKATANI |
Corrections Issued | 5/30/2001 | DOUG NAKATANI |
Issued | 6/28/2001 | BOSCO TANG |
Permit Finaled | 6/24/2002 | BENOIT BEAULIEU |
Permit Application Clearance Information
Miscellaneous | Cleared | 6/5/2001 | RAQUEL DICKENSON |
ZA Case | Cleared | 6/5/2001 | RAQUEL DICKENSON |
ZI | Cleared | 6/5/2001 | RAQUEL DICKENSON |
Building Permit Clearance | Cleared | 6/25/2001 | WALLACE HASBROUCK |
DAS Clearance | Cleared | 6/25/2001 | OCTAVIO LOZANO |
Sewer availability | Cleared | 6/25/2001 | RANDALL MORIMOTO |
Contact Information
Architect | Davidson, Donald Lee; Lic. No.: C7497 | 11279 LAURIE DRIVE STUDIO CITY, CA 91604 |
Contractor | Cantamar Construction Of San Diego; Lic. No.: 622942-B | 4319 DATE AVEUNE LA MESA, CA 91941 |
Inspector Information
ROBERT DAVIS, (818) 374-1128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Rough-Frame | 7/12/2001 | Corrections Issued | ALBERT HAAS |
Drywall Nailing | 9/18/2001 | Partial Approval | ALBERT HAAS |
Rough-Frame | 9/18/2001 | Partial Approval | ALBERT HAAS |
Drywall Nailing | 9/20/2001 | Partial Approval | ALBERT HAAS |
Rough-Frame | 9/20/2001 | Partial Approval | ALBERT HAAS |
Rough-Frame | 9/26/2001 | Conditional Approval | ALBERT HAAS |
Deputy Inspection | 10/3/2001 | Approved | ALBERT HAAS |
Deputy Inspection | 10/12/2001 | Approved | ALBERT HAAS |
Rough-Frame | 10/17/2001 | Partial Approval | ALBERT HAAS |
Drywall Nailing | 10/24/2001 | Approved | ALBERT HAAS |
Final | 10/30/2001 | Partial Approval | ALBERT HAAS |
Rough-Frame | 10/31/2001 | Partial Approval | ALBERT HAAS |
T-Bar Ceiling | 11/16/2001 | Approved | ALBERT HAAS |
Final | 11/28/2001 | Partial Approval | ALBERT HAAS |
Special/Order Compliance | 4/25/2002 | OK to Issue CofO | BENOIT BEAULIEU |