356-358 W 81ST ST
Certificate Information: 356-358 W 81ST ST
- Application / Permit
- 01010-10000-00229
- Plan Check / Job No.
- B01LA00299
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX 2,464 SQ. FT. LIVING AREA
- Permit Issued
- Issued on 11/8/2001
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 8/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Fees Due | 1/26/2001 | LORRAINE ALEMAN |
| Fees Due | 1/26/2001 | LEANDRO BANGUGUILAM |
| Submitted | 1/26/2001 | JANICE BATSON |
| PC Assigned | 2/2/2001 | HENRY YUN |
| Corrections Issued | 2/15/2001 | JAHANSHAH POURHASSAN |
| Issued | 11/8/2001 | MAXX SKOULPHONG |
| Permit Expired-Status Void | 5/4/2009 | FELIPE PENICHE |
| Re-Activate Permit | 6/29/2023 | DONALD CRICHLOW |
| CofO in Progress | 8/9/2023 | MICHAEL LEWIS |
| Permit Finaled | 8/11/2023 | RONALD MYRICK |
| CofO Issued | 8/11/2023 | RONALD MYRICK |
| Permit Finaled | 8/11/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Dwelling unit tax | Cleared | 9/6/2001 | ANGELA GONZALEZ |
| (New) Address approval | Cleared | 9/18/2001 | DAVID CHIN |
| A-Permit | Cleared | 9/27/2001 | VALENTINO PUEBLOS |
| Sewer availability | Cleared | 9/27/2001 | VALENTINO PUEBLOS |
| Roof/Waste drainage to street | Cleared | 9/28/2001 | DANNY HO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Goble, Daniel E Jr; Lic. No.: C13372 | 2834 RIO CLARO DR LA PUENTE, CA 91745 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 11/13/2001 | Approved | REINALDO SANCHEZ |
| ELECTRICAL-Rough | 11/13/2001 | Approved | REINALDO SANCHEZ |
| HVAC-Rough | 11/13/2001 | Approved | REINALDO SANCHEZ |
| Insulation | 11/13/2001 | Approved | REINALDO SANCHEZ |
| PLUMBING-Rough | 11/13/2001 | Approved | REINALDO SANCHEZ |
| Excavation/Setback/Form/Re-Bar | 12/10/2001 | Not Ready for Inspection | JOHNNY VERCHER |
| SGSOV-Seismic Gas S/O Valve | 3/14/2003 | SGSOV Order to Comply | JACKIE GOMEZ |
| SGSOV-Seismic Gas S/O Valve | 3/18/2003 | SGSOV Order to Comply | DENNIS STEWART |
| SGSOV-Seismic Gas S/O Valve | 4/4/2003 | SGSOV Order to Comply | PATRICK KELLY |
| SGSOV-Seismic Gas S/O Valve | 5/21/2003 | SGSOV Order to Comply | DAVID CAPTAIN |
| SGSOV-Seismic Gas S/O Valve | 5/30/2003 | Order to Comply Issued | DAVID CAPTAIN |
| SGSOV-Seismic Gas S/O Valve | 1/26/2004 | SGSOV Order to Comply | GARY ESKAY |
| Final | 8/26/2008 | Not Ready for Inspection | MARK RUDE |
| Final | 8/28/2008 | Not Ready for Inspection | MARK RUDE |
| Final | 5/1/2009 | Corrections Issued | FELIPE PENICHE |
| Final | 5/1/2009 | Permit Expired-Status Void | FELIPE PENICHE |
| SGSOV-Seismic Gas S/O Valve | 5/1/2009 | SGSOV Not Ready | FELIPE PENICHE |
| Drywall Nailing | 6/29/2023 | Corrections Issued | DONALD CRICHLOW |
| Final | 7/5/2023 | Partial Inspection | MICHAEL LEWIS |
| Final | 7/7/2023 | Corrections Issued | MICHAEL LEWIS |
| Final | 8/4/2023 | OK to Issue CofO | MICHAEL LEWIS |