15209 W DEVONSHIRE ST 91345

Certificate Information: 15209 W DEVONSHIRE ST 91345

Application / Permit
00014-20000-02943
Plan Check / Job No.
--
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(22) Storage - incidental
Work Description
CONVERT (E) 18'X20' GARAGE INTO STORAGE AND ADD 8'6"X18' ADDTIONAL STORAGE. ADD 18'x18' CARPORT.
Permit Issued
Issued on 6/1/2000
Issuing Office
Valley
Current Status
CofO Issued on 1/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Issued 6/1/2000 LOUCIN ARTINIAN
Permit Expired-Status Void 8/5/2022 ROBERT GOLD
Re-Activate Permit 11/17/2022 ROBERT GOLD
CofO in Progress 12/15/2022 ROBERT GOLD
No Progress 1/5/2023 ROBERT GOLD
CofO in Progress 1/18/2023 ROBERT GOLD
CofO Issued 1/18/2023 MICHAEL SMITH
Permit Finaled 1/18/2023 MICHAEL SMITH

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 12/29/2000 Not Ready for Inspection GINO HAMILTON
ELECTRICAL-Rough 12/29/2000 Not Ready for Inspection GINO HAMILTON
Excavation/Setback/Form/Re-Bar 12/29/2000 Not Ready for Inspection GINO HAMILTON
HVAC-Rough 12/29/2000 Not Ready for Inspection GINO HAMILTON
PLUMBING-Rough 12/29/2000 Not Ready for Inspection GINO HAMILTON
Excavation/Setback/Form/Re-Bar 5/3/2001 Not Ready for Inspection GINO HAMILTON
Footing/Foundation/Slab 5/3/2001 Not Ready for Inspection GINO HAMILTON
Piling/Pier/Caisson 5/3/2001 Not Ready for Inspection GINO HAMILTON
Underground Mechanical 5/3/2001 Not Ready for Inspection GINO HAMILTON
BUILDING-Rough-Frame 5/25/2001 Corrections Issued ALBERT ACOSTA
BUILDING-Rough-Frame 5/29/2001 Corrections Issued ALBERT ACOSTA
ELECTRICAL-Rough 5/29/2001 Corrections Issued ALBERT ACOSTA
BUILDING-Rough-Frame 5/30/2001 Approved ALBERT ACOSTA
Footing/Foundation/Slab 5/30/2001 Partial Approval ALBERT ACOSTA
Footing/Foundation/Slab 6/8/2001 Approved ALBERT ACOSTA
Excavation/Setback/Form/Re-Bar 6/18/2001 Corrections Issued GINO HAMILTON
Footing/Foundation/Slab 6/18/2001 Corrections Issued GINO HAMILTON
PLUMBING-Rough 6/18/2001 Corrections Issued GINO HAMILTON
Underground Mechanical 6/18/2001 Corrections Issued GINO HAMILTON
Final 4/16/2008 Corrections Issued KEN KUROWSKI
Final 5/29/2013 No Access for Inspection DONALD GALLAGHER
Final 6/25/2013 No Access for Inspection DONALD GALLAGHER
BUILDING-Rough-Frame 8/2/2022 Not Ready for Inspection JAVIER RAMOS JR
Special/Order Compliance 8/5/2022 Permit Expired-Status Void ROBERT GOLD
Final 11/29/2022 OK to Issue CofO JAVIER RAMOS JR
Final 1/4/2023 Corrections Issued ROBERT GOLD